The Macomb Daily

PUBLIC SAFETY BUILDING COULD OPEN BY JANUARY

COVID-19 set constructi­on back by about three months

- By Nicole Tuttle

The Macomb Township Fire Department andM acomb County Sheriff’s Office are hoping to ring in 2021 with a new, completed Joseph E. Koss Public Safety Building.

The new public safety building is being built near 23 Mile Road and Alma Drive, east of Romeo Plank Road in Macomb Township. It is on the same property as a township senior center and broadcast media center.

Macomb Township Fire Chief Robert Phillips said work is underway with numerous trade unions going at it.

“Currently the masons are finishing the brick on the exterior, the interior metal and block walls are under constructi­on,” Phillips said. “The shingles are being installed, the HVAC system is being installed, the fire suppressio­n system is being installed, the windows are going in, the electrical and plumbing is continuing, the concrete on the exterior is being poured and site work is continuing in order to get the front parking area finished and ready for concrete before the cold weather arrives.”

He stated the majority of the brick and block on the building is complete, and the majority of the concrete has been poured. He added trusses and sheeting are complete and the roof is anticipate­d to be done shortly.

“COVID has delayed the project approximat­ely three months,” Phillips said. “We were originally scheduled to take occupancy of the building this month. It is now scheduled for mid-January 2021.”

Oil intercepto­rs were installed in August and are operationa­l. A payment issue is being worked out between the township attorney and Anderson, Eckstein and Westrick’s attorney.

“The building will have wifi access points through-

out that will allow fire and sheriff to utilize the technology provided by COMTEC as part of the contract that we have with them. The fire truck and sheriff cars all have mobile data terminals in them and the building will have access to that informatio­n on monitors located throughout the building,” Phillips said. “It has been built to eliminate cross-contaminat­ion by reducing the amount of toxins from vehicle exhaust and to keep contaminat­ed clothing from entering the administra­tive portion of the building.”

The project originated a few years ago when the Macomb County Department of Roads notified the township of its plans to widen 23 Mile Road from Romeo Plank Road to North Avenue. With widening, the 1952 Macomb Township Fire Station One and the Macomb County Sheriff’s Office substation would have been right on the edge.

“I have been working on this since we found out in

December 2015 that 23 Mile Road was going to be widened and the previous station would be too close to the new road,” Phillips said.

In 2016 Phillips held discussion­s with James VanTifin, the township engineer, and then-planning director Patrick Meagher to determine utilities, septic fields, and other items. After ascertaini­ng what was needed and would fit on the property, the next step was to obtain Macomb Township Board of Trustees approval to seek an architectu­ral design service. The bid was awarded for the architectu­ral design service in the fall of 2017 to Anderson, Eckstein and Westrick. Most of 2017 was spent doing design and budgetary numbers.

In September 2018, the township board awarded a constructi­on contract for the building to Bernco Inc. of St. Clair Shores for $11.06 million.

The contract had a contingenc­y of $875,000 built into it, and about an additional $300,000 was estimated to be needed for sales tax. About $700,000 was needed for costs such as furniture, lockers and other

items. Total cost for storm water detention for the new public safety building, the broadcast media center and the senior citizens building was approved by the board of trustees in May 2019 at approximat­ely $700,000. In December 2018, the sheriff’s office substation was demolished, with the sheriff’s office temporaril­y operating out of the township’s broadcast media center. In the spring of 2019, constructi­on on the site began.

“The sheriff’s portion of the building is still under constructi­on and is not able to be used,” Phillips said.

However, Phillips said the sheriff garage portion of the new building, located at the back of the building on Alma Drive, is about 90 percent done and is being used to house materials arriving daily for the subcontrac­tors.

In February 2020 a decommissi­oning ceremony was held for Fire Station One shortly before demolition began, with fire department personnel housed temporaril­y in a constructi­on trailer. Phillips said that presently, there are nine full-time firefighte­rs assigned to the former Station

One area, with three on each day working 24-hour shifts. He said there are also 15 auxiliary and paid on-call firefighte­rs that are assigned to the former Station One area.

Phillips said the department of roads has agreed to delay the section of road widening that would affect the new building until the building is open.

“The only portion of the building in use is the apparatus bays that house the fire trucks,” Phillips said. “We moved into the bays in February 2020.”

The JosephE. Koss Public Safety Building is projected to be sufficient for community needs for about 50 years. The 37,000-squarefoot building will include five drive-through bays for the fire department, space for 14 sheriff’s office vehicles, offices for police and fire personnel, a shared break room, kitchen, exercise room, training room and conference room, locker rooms for both department­s and firefighte­r dorms. Public access for the new building will be off of Alma Drive and the public parking lotwill be along 23 Mile Road.

 ?? PHOTO COURTESY OF ROBERT PHILLIPS ?? Although the onset of COVID-19and related restrictio­ns caused a delay for about three months, the new Joseph E. Koss Public Safety Building is now progressin­g in Macomb Township.
PHOTO COURTESY OF ROBERT PHILLIPS Although the onset of COVID-19and related restrictio­ns caused a delay for about three months, the new Joseph E. Koss Public Safety Building is now progressin­g in Macomb Township.
 ?? NICOLE TUTTLE — FOR THE MACOMB DAILY ?? The Joseph E. Koss Public Safety Building in Macomb Township is under constructi­on but could be open by January 2021.
NICOLE TUTTLE — FOR THE MACOMB DAILY The Joseph E. Koss Public Safety Building in Macomb Township is under constructi­on but could be open by January 2021.

Newspapers in English

Newspapers from United States