26 Mile Road Bridge
26 Mile Road bridge in Macomb Township and Ray Township over North Branch Clinton River Starting April 25, 26Mile Road will be closed to thru traffic from Broughton Road to Ray Center Road. A detour will be posted. Drivers should seek alternate routes when possible. Project consists of bridge superstructure replacement and approach work as part of MDOT Bridge Bundle Program. Project duration April 25-October 2022.
31 Mile Road Bridge
31Mile Road Bridge over Tupper Brook Drain in Ray Township. 31Mile Road will be closed to thru traffic from Hartway Road to North Avenue. A detour will be posted. Drivers should seek alternate routes when possible. Project consists of bridge
superstructure replacement and approach work as part of MDOT Bridge Bundle Program. Project duration April 25-June 2022.
33 Mile Road Bridge
33Mile Road Bridge over East Branch Coon Creek.
33Mile Road will be closed to thru traffic from North Avenue to Omo Road. A detour will be posted. Drivers should seek alternate routes when possible. Project consists of bridge superstructure replacement and approach work as part of MDOT Bridge Bundle Program. Project duration March 14-May 2022.
Hayes Road
Hayes Road from 10Mile Road to 11Mile Road in Eastpointe. Hayes Road will be down to one way traffic. A detour will be posted. Drivers should seek alternate routes when possible. Project consists of mill and asphalt overlay. Project duration April 18-May 31, 2022.
Metropolitan Parkway (16 Mile Road) in Sterling Heights
Metropolitan Parkway from Dequindre Road to Ryan Road. Road will remain open to thru traffic with lane closures in place during resurfacing and construction operations. Project consists of mill, base repair and asphalt overlay. Project duration April 12-July 2022.
Mound Road
Mound Road from I-696 to M-59in Sterling Heights and Warren. Road reconstruction part of Innovate Mound project. Traffic and business access will remain open during the duration of the project. Drivers should expect delays and seek alternate routes when possible. Project duration is August 2021
to 2024.
New Haven Road Bridge
New Haven Road Bridge in
Lenox Township over east branch Coon Creek
New Haven Road will be closed to thru traffic from Omo Road to 28Mile Road for bridge replacement and approach work. A detour will be posted. Drivers should seek alternate routes. Project duration March 9-July 2022.
Schoenherr Road
Schoenherr Road between the Plumbrook Drain and north of
Clinton River Road in Sterling Heights. Road will remain open to thru traffic with lane closures in place during rehabilitation operations. Single lane closures will only be in place during work operations. Work is part of the bridge rehabilitation and includes ashpalt repairs and expoxy overlay. Project duration is April 11-June 2022.
M-3 (Gratiot Avenue)