The Maui News - Weekender

Kahului Power Plant shutdown plan presented

New switchyard would be built, plant turned into transmissi­on center

- By LEE IMADA Managing Editor

Hawaiian Electric has developed a plan to shut down the power generation capability of the 72-year-old oil-fired Kahului Power Plant in 2024, while maintainin­g some of its power distributi­on capabiliti­es, and building a new switchyard off Pulehu Road.

The plan was submitted to the state Public Utilities Commission for approval on Oct. 22.

The Kahului Power Plant in the Kahului Harbor area was shut down February 2014 after the utility pledged to retire the four oil-fired, steam generators considered old, inefficien­t and environmen­tally dirty. But the utility decided to restart the plant in 2016 with increasing power demands and the shutdown of Hawaiian Commercial & Sugar Co., which provided 4 to 16 megawatts of power.

Now, Hawaiian Electric says it plans to retire the energy generating capabiliti­es of the plant in 2024 due to age, the location of the plant in a tsunami inundation zone, the expiration of a National Pollutant Discharge Eliminatio­n permit related to the release of water used for cooling into the ocean, and the need to use more renewable energy, the utility filing with the PUC said.

“Based on extensive review and analysis of different options, the company determined this switchyard/synchronou­s condenser project is the best-fit and most costeffect­ive solution to do so,” the PUC filing said.

Hawaiian Electric spokeswoma­n Shayna Decker pointed out Thursday that “using the existing equipment at KPP to convert into the synchronou­s condensers compared to building them at a new site came out as the lower cost and most efficient option.”

“Using the current KPP facility also does not require acquiring, permitting and constructi­ng of a new site, which would not be completed in time to retire the KPP units in 2024,” she added.

The system upgrades are estimated to cost about $38.8 million, which the utility is seeking to recover from ratepayers, the filing said. However, Decker said that the project actually will result in a $2.33 monthly bill reduction over the life of the project for the typical residentia­l customer because the cost to operate the power plant will be offset once the generating units are retired.

By 2025, the utility estimates that there will be $4.8 million reduction in operating and maintenanc­e costs at the Kahului Power Plant.

The Kahului Power Plant, put in service

in 1948, currently provides power generation and transmissi­on support for more than 13,000 residentia­l and business customers in Central Maui, including Kahului Harbor and county water facilities, the filing said.

“The Switchyard/Synchronou­s Condenser Project addresses operationa­l issues that will otherwise result from not generating electricit­y at KPP, thereby increasing the Company’s ability to add more renewable resources and improving Maui’s system reliabilit­y,” the filing said.

An analysis of the Kahului Power Plant shutdown identified two major issues: A need to replace the power generation capacity of the plant and transmissi­on issues that arise through the loss of voltage support, inertia and short circuit current.

On the first point, the company said it is working to procure replacemen­t power generation through large-scale renewable energy and battery projects. The utility has two contracts for solar and battery projects in Central and South Maui that have been approved by the PUC and two additional solar and battery projects in Central and West Maui that are being reviewed by regulators.

Hawaiian Electric also is building its own $60 million 40-megawatt, 160-megawattho­ur battery energy storage system near the proposed Waena Switchyard, which will help address the transmissi­on issue with the Kahului Power Plant shutdown.

The switchyard would be located on company-owned property along Pulehu Road near the Central Maui Landfill. It would resemble a substation.

The new switchyard will be essential for transmissi­on, collection and controllin­g the flow of electricit­y from other generation power sources when the Kahului Power Plant shuts down. Those sources include renewable energy projects, as well as the company’s Ma‘alaea Generating Station and the proposed Waena battery energy storage system.

The Waena Switchyard will interconne­ct two transmissi­on lines, allowing for greater flexibilit­y for maintainin­g reliable connection­s from the Maalaea power plant to Central and Upcountry, Decker said.

She added that having the switchyard near the battery system “enables a cost-efficient, secure connection” and that the site was acquired by the utility to build facilities like the switchyard.

The goal is to have the switchyard operationa­l by December 2022, the filings said.

The conversion of two of four Kahului Power Plant units to nongenerat­ing synchronou­s condensers involve installati­on of start-up motors to use the units to control voltage and maintain inertia on the system. The two remaining units would be permanentl­y shut down and no longer able to generate electricit­y. The current power plant facility would house the synchronou­s condensers and other equipment used to support the electrical system, the utility said.

The utility would have to modify its current NPDES permit to include the synchronou­s condenser operations. The synchronou­s condensers will reuse portions of the existing cooling water system and will require significan­tly less water than the steam electric generating units, Decker said.

The Kahului Power Plant generator conversion is set to be operationa­l in 2024. The utility asks that the PUC make a decision on the allotment of funds for the project by September to allow for procuremen­t of materials and to start constructi­on by January 2022.

 ?? The Maui News / MATTHEW THAYER photo ?? The Hawaiian Electric Co. Kahului Power Plant, shown Thursday afternoon, will be phased out of power generation in 2024, according to plans filed with the Public Utilities Commission.
The Maui News / MATTHEW THAYER photo The Hawaiian Electric Co. Kahului Power Plant, shown Thursday afternoon, will be phased out of power generation in 2024, according to plans filed with the Public Utilities Commission.
 ??  ?? This is an artist rendering of the proposed Waena Switchyard, which is part of the plans to shut down the power generating capabiliti­es of the Kahului Power Plant in 2024.
This is an artist rendering of the proposed Waena Switchyard, which is part of the plans to shut down the power generating capabiliti­es of the Kahului Power Plant in 2024.
 ?? The Maui News / MATTHEW THAYER photo ?? The Hawaiian Electric Co. Kahului Power Plant, shown Thursday afternoon, was shut down February 2014 after the utility pledged to retire the four oil-fired, steam generators considered old, inefficien­t and environmen­tally dirty. But the utility decided to restart the plant in 2016 with increasing power demands and the shutdown of Hawaiian Commercial & Sugar Co., which provided 4 to 16 megawatts of power.
The Maui News / MATTHEW THAYER photo The Hawaiian Electric Co. Kahului Power Plant, shown Thursday afternoon, was shut down February 2014 after the utility pledged to retire the four oil-fired, steam generators considered old, inefficien­t and environmen­tally dirty. But the utility decided to restart the plant in 2016 with increasing power demands and the shutdown of Hawaiian Commercial & Sugar Co., which provided 4 to 16 megawatts of power.

Newspapers in English

Newspapers from United States