The Middletown Press (Middletown, CT)

City to consider options to fund new $4M rec complex

- By Cassandra Day

MIDDLETOWN — Members of the Common Council are considerin­g options on how to fund the new $4 million Middletown Recreation Center, which will occupy the unrazed portion of the old middle school.

The gymnasium, auxiliary gym, pool, and office area at the former 42,000-square-foot Woodrow Wilson Middle School are being repurposed for the project.

The comprehens­ive energy plan at the facility, which was replaced this month by the new energy-efficient Beman Elementary School, was presented to the Common Council members last week.

For the past six years, the recreation office has been at the senior center on Durant Terrace. Before that, it was at Riverview Center on Main Street.

The project was initiated a few years ago when the new middle school plans were developed, according to Public Works Deputy Director Chris Holden. The initial budget did not include a number of issues that

needed to be addressed, he told council members last week.

Landmark Architects developed specificat­ions for the project.

Members of the Middletown

Clean Energy Task Force, who had experience with the Water & Sewer Department solar rooftop array installati­on, helped brainstorm ways to make the building as sustainabl­e as possible, Holden added.

“I thought we’d have a few more years left in the life of the roof, but during recent

investigat­ions with the building department, it was determined that was one of the critical items that we needed to do first,” he told council members.

He estimates it will cost between $600,000 and $700,000 to replace the roof, which is above the original budget, Holden said. “We had to come up with creative ways to be able to include that in part of our project.”

Landmark conducted a feasibilit­y study “to determine the highest and best use of the remaining” sections of Woodrow Wilson, President Paul Pizzo told councilors. It determined a complete renovation would cost $8.5 million spread over

three phases and several years, he said.

Phase 1 was approved for $1.5 million as part of the $55 million 21st Century Bond package, Pizzo said, adding that any further funding would require additional capital expenditur­es.

Council Majority Leader Gene Nocera said Wednesday the project is estimated to cost $4 million if not done in increments. “The city is exploring a more comprehens­ive plan than to try to do it over a three-year period.”

If the work was done in phases, he said, there would be additional costs in the future. “We’re still debating the financiall­y wise thing to

do,” he added.

The solar array, which would resemble the one at Beman, would achieve a net-zero carbon impact, Nocera said.

Nocera said there are several options: Take additional monies out of the infrastruc­ture bond to replace the roof, leasing the solar equipment, use American Rescue Act monies or a combinatio­n of the three, he said. “It doesn’t seem to be economical­ly sound to do it piecework.”

The pool has not been able to be “robustly” used by the Middletown High School swim team for some time due to the constructi­on, Nocera said. It was formerly

used twice a week, and is also utilized by the Vet’s Swim Team and other groups.

“They are fed up with continued delays. We will get this online. Time is ticking. It has to be done. It will bring us into the 21st century. Why would we go backward?” the councilman said.

The pool is in good shape, he added. Officials hope to get it up and running by February or March.

The council will consider the plan at its October meeting.

 ?? Gene Nocera / Contribute­d photo ?? Work has begun on the new Middletown Recreation Center at the site of the former Woodrow Wilson Middle School.
Gene Nocera / Contribute­d photo Work has begun on the new Middletown Recreation Center at the site of the former Woodrow Wilson Middle School.

Newspapers in English

Newspapers from United States