The News Herald (Willoughby, OH)

Stanton Park bluff stabilizat­ion nears finish

- By Bill DeBus wdebus@news-herald.com

The bluff stabilizat­ion project at Bill Stanton Community Park in Madison Township is taking a bit longer than expected to complete.

This week, crews from J Severino Constructi­on of Ashtabula placed additional topsoil onto a hillside at the park that overlooks Lake Erie.

Madison Township Trustee Kenneth Gauntner Jr. said he was watching some of the constructi­on activity, which involved bulldozers and trucks, on the morning of Aug. 4.

“Our intention never was to create a beautiful beach, it was to save Stanton Park from falling into the lake, and to capture all of that groundwate­r that was really the source of the erosion. The highpressu­re water table is the bigger problem than anything.” — Madison Township Trustee Kenneth Gauntner Jr.

Adding the final layer of topsoil, which had been scraped off the bluff when it was regraded, would be followed by the contractor putting down grass seed and erosion-control matting, Gauntner said.

The matting is a biodegrada­ble covering that stabilizes soil on a hillside while grass is germinatin­g and taking hold, he added.

Although Madison Township owns Stanton Park, which is located at 5585 Chapel Road, the Lake County Ohio Port and Economic Developmen­t Authority is serving as administra­tor of the project.

David Anderson, the authority’s executive director, said on the afternoon of Aug. 5 that Severino intended to finish depositing topsoil on the hillside by the end of the same day. The contractor expected to start putting in grass seed and matting on Aug. 7.

Severino began working in early April on the project, which is being conducted to stabilize a severely eroded bluff at Stanton Park along the Lake Erie shoreline.

The contractor already graded what once was a steep, 70-feet high bluff into a more gentle, contoured hillside. Other parts of the project that have been completed were installati­on of undergroun­d drains to divert groundwate­r and the creation of wet and dry beaches on the shoreline.

The authority’s contract with Severino called for a project completion date of June 1. An extension was granted to June 30, but that deadline was missed, Gauntner said.

Recently, some contract issues brought work to a halt for a few weeks, but those matters were ironed out, Gauntner said.

“Severino came back on the job and now they’re doing what they were contracted to do,” Gauntner said. “I’m very pleased to see it.”

However, Gauntner expressed disappoint­ment that grass isn’t being planted on the hillside until early August.

“The quicker we can get the grass to take hold, the better off we’re going to be, and the window is closing quickly,” he said. “We’ve got between now and probably mid-October to get anything to grow there that will hold up over the winter. So that’s still a concern of mine.”

At this point, the township plans to keep fencing in place to keep park visitors from wandering onto the hillside or trying to walk down to the water’s edge.

“It probably will be restricted well into next year,” Gauntner said.

Gauntner said it’s important for residents to understand that the Stanton Park bluff stabilizat­ion project isn’t being done to create a beach that would be comparable to the one at Madison Township Park.

“Our intention never was to create a beautiful beach, it was to save Stanton Park from falling into the lake, and to capture all of that groundwate­r that was really the source of the erosion,” he said. The highpressu­re water table is the bigger problem than anything.”

Over the last five years alone, the park has lost about 40 to 50 feet of land, north to south, because of erosion that has decimated the bluff.

The bluff stretches about 1,000 lineal feet from east to west.

Underdrain­s installed as part of the stabilizat­ion project so far have done a great job of capturing groundwate­r that had been running between layers of clay and sand, Gauntner said. Because of the highpressu­re water table, that groundwate­r was causing blowouts and slumping on the face of the bluff.

The displaced soil then would slide to the bottom of the bluff and get washed into Lake Erie.

Along with the underdrain­s, three pipes have been put in place that divert groundwate­r into Lake Erie constantly.

“Water is just pouring out,” Gauntner said.

Madison Township is paying for project with up to $490,000 in federal funding that was earmarked in 1998 to address only erosion control at Stanton Park.

“That money’s been sitting with (Ohio Department of Transporta­tion), not with the township, because the park was bought with (federal) transporta­tion funds,” Gauntner said.

In addition, the Lake County Ohio Port and Economic Developmen­t Authority obtained a state capital grant of about $300,000 for Stanton Park about five years ago.

The money was used to relocate park utilities that were situated in the same area targeted for the bluff stabilizat­ion project.

 ?? BILL DEBUS — THE NEWS-HERALD ?? A worker from J Severino Constructi­on of Ashtabula maneuvers a bulldozer on Aug. 5 at the site of the bluff stabilizat­ion project at Bill Stanton Community Park in Madison Township.
BILL DEBUS — THE NEWS-HERALD A worker from J Severino Constructi­on of Ashtabula maneuvers a bulldozer on Aug. 5 at the site of the bluff stabilizat­ion project at Bill Stanton Community Park in Madison Township.

Newspapers in English

Newspapers from United States