The Oklahoman

Edmond officials promise stormwater relief is coming

- Staff Writer dbaldwin@oklahoman.com BY DIANA BALDWIN

EDMOND — Property owners are so frustrated they demanded this week that no more building permits be issued in downtown Edmond until ongoing stormwater flooding problems are corrected.

Saeed Zahrai, head of XCESS LLC, wrote in a letter to City Manager Larry Stevens that city officials have “intentiona­lly and willfully violated” the municipal code by permitting land disturbanc­es that have created a public hazard on property within the city limits.

“This noncomplia­nce practice must stop until the drainage problems, caused by the city of Edmond, are corrected,” Zahrai wrote.

Downtown property owners also crowded into a special meeting of the Central Edmond Urban District Board this week where a site plan for The Campbell, a mixed-use project, in downtown was recommende­d for approval. City council will make a final decision Aug 14.

“The room was full of downtown people at the meeting expressing concerns regarding drainage

and flooding problems downtown,” said City Planner Jan Ramseyer Fees. “They were asking for no more developmen­t downtown until the stormwater drainage project authorized in 2015 is finished.”

Zahrai and his company sued the city in 2010, claiming that on or about Oct. 29, 2009, flood damage occurred on the northeast corner of Hurd and Broadway. Similar flooding has continued over the last seven years.

The lawsuit is still pending in Oklahoma County District Court. Randel Shadid, attorney for XCESS, said he continues to amend the lawsuit each time downtown businesses flood.

“I think they are just frustrated while water keeps lapping at the bottom of the door,” Shadid said.

Koorosh Zahrai, vice president of business developmen­t of Plaza USA and Saeed Zahrai’s son, alleged this week that the city “stole the money” originally to be spent for downtown stormwater drainage and parking improvemen­ts.

“There have been zero improvemen­ts,” the younger Zahrai said. “The city has absolutely neglected the storm water. Basically, they stole the money for Interstate 35 and Covell.

“This is a very important issue and we can’t go on any longer.”

City officials disagree. They said they have been working on the downtown stormwater improvemen­t project since September 2015 when the city council approved $2.6 million for the design work and constructi­on.

”Any perception that this project is not moving forward is not true,” Stevens said.

The money is there and has been there since 2015, he said.

In May 2016, city officials approved spending $1.35 million of the $2.6 million downtown stormwater money for the remainder of the constructi­on of Covell Road and Interstate 35 to Fairfax Boulevard.

“The downtown stormwater project was still in the design phase and wasn’t going to be ready for bid by the end of the fiscal year in June,” said Assistant City Manager Steve Commons.

He said the entire $2.6 million was encumbered and was always in the 2000 Capital Improvemen­t Sales Tax Fund.

“When we are ready to encumber the funds this year we will simply do a supplement­al appropriat­ion to access those funds in the current 201718 fiscal year,” Stevens said. “This is not a unique occurrence for us, as it has been done on numerous occasions.

“The time frames for constructi­on projects do not always fall neatly into the original budget year.”

Cabbiness Engineerin­g was hired to do the design work on downtown stormwater drainage on

Oct. 5, 2015, for $126,305. The design plans for the project are almost complete, Stevens said.

“These will be finalized, with final quantities, once we receive the relocation plans from the utilities,” Stevens said. “Our people will have met with all these utilities to determine everything that is in the way of the new storm sewer.”

Utility relocation plans are to be submitted to the city in 60 days.

“Once we get those and expedite their approval, the relocation­s will start,” Stevens said.

Plans are to have the relocation­s completed and the project out to bid in January. Constructi­on is estimated to take six to eight months, the city manager said.

The project involves the constructi­on of about a half mile of new storm sewer, starting west of the AT&T building and going north, ultimately ending at the railroad tracks at Campbell and Edwards and draining into the downtown regional detention area.

The sewer now is a 42to 48-inch clay pipe that is old and undersized. The new pipe will be fiberglass and at least 60 inches in size.

City officials warned that this downtown project is going to be “very disruptive” for services and businesses.

“Mr. (Steve) Manek said that this will be the most difficult project we have had to build in his tenure as city engineer, due to the limited space and all the disruption­s that will occur during the utility relocation­s and the actual project itself,” Stevens said. “The project will proceed a block at a time. Sections of Campbell will need to be closed.

“Parking in the downtown area will be significan­tly affected — as one example, the parking in front of Pete Reeser’s office building will be blocked off for a period of time.

“Our people are trying to identify as many of the conflicts as possible before constructi­on, so the project will go as smoothly as possible when constructi­on begins.”

 ?? [PHOTO PROVIDED] ?? Workers in downtown Edmond work on a sanitary sewer project. City officials say this photograph illustrate­s the tight confines of the undergroun­d area where a new stormwater pipe would have to be installed to alleviate flooding downtown.
[PHOTO PROVIDED] Workers in downtown Edmond work on a sanitary sewer project. City officials say this photograph illustrate­s the tight confines of the undergroun­d area where a new stormwater pipe would have to be installed to alleviate flooding downtown.

Newspapers in English

Newspapers from United States