The Oklahoman

Key design change stymied Fla. bridge cost, schedule

- BY JASON DEAREN AND JENNIFER KAY

MIAMI — Constructi­on of the pedestrian bridge that collapsed and killed six people in the Miami area was behind schedule and millions over budget, in part because of a key change in the design and placement of one of its support towers.

Documents obtained by The Associated Press through a public-records request show that the Florida Department of Transporta­tion in October 2016 advised Florida Internatio­nal University and its contractor­s to move one of the bridge’s main support structures 11 feet north to the edge of a canal, widening the gap between the crossing’s end supports and requiring some new structural design.

The span’s signature, 109-foot-tall pylon was to be built atop a base at the span’s northern end. It was designed for basic support and to contribute to the aesthetics of the bridge, which was touted as an architectu­ral marvel that would connect the rapidly growing university to the nearby community of Sweetwater. In their winning 2015 proposal, designers said the bridge provided “spectacula­r views” for both pedestrian­s using the bridge and drivers passing beneath it. They added that the tower could serve as a safety feature because it would have an “eagle-eyed location” for additional lighting and security cameras.

Videos of Thursday’s collapse show that the concrete, prefabrica­ted segment of the bridge started crumbling on the same end of the span where the tower redesign occurred, two days after an engineer on the project reported cracks in the same location. The segment that failed had been placed atop the pylon’s footing, and the taller tower section was to be installed later.

U.S. Transporta­tion Secretary Elaine Chao has ordered her department’s inspector general to conduct an audit of the bridge, according to a news release Tuesday from the U.S. Department of Transporta­tion. The agency awarded millions of dollars to the project.

It is still unclear if the design change contribute­d to the failure. But emails between the school, contractor­s, Sweetwater city officials and permitting agencies show a project that was behind schedule, which had officials worried that further delays could jeopardize the federal funding.

When the bridge collapsed, the project was already running about $2.6 million over its $9.4 million initial budget, cost-tracking documents from February show. Originally scheduled to be completed in July, the finish date had been pushed back to January 2019.

 ?? [PEDRO PORTAL/ THE MIAMI HERALD VIA AP] ?? This March 10 photo shows the main span of the a pedestrian bridge being positioned to connect the city of Sweetwater to Florida Internatio­nal University near Miami. The 950- ton new bridge collapsed Thursday over several cars causing fatalities and...
[PEDRO PORTAL/ THE MIAMI HERALD VIA AP] This March 10 photo shows the main span of the a pedestrian bridge being positioned to connect the city of Sweetwater to Florida Internatio­nal University near Miami. The 950- ton new bridge collapsed Thursday over several cars causing fatalities and...

Newspapers in English

Newspapers from United States