The Oklahoman

Power surge

Cimarron Electric continues rapid growth as it keeps pace with oil and gas activities in the STACK play.

- BY JACK MONEY Business Writer jmoney@oklahoman.com

KINGFISHER — Up until a few years ago, Cimarron Electric Cooperativ­e was a typical rural power provider that distribute­d about 50 megawatts of power to about 13,300 locations spread across about 9,000 square miles.

Its members were people who were using electricit­y to power water wells, some homes and barns.

Then, the oil and gas industry began moving in, and everything changed.

“What I liken it to is taking a city about the size of Guthrie into the middle of nowhere, dropping it and saying, serve that load without any infrastruc­ture already in place,” explained Reed Emerson, the cooperativ­e’s senior vice president of operations and engineerin­g.

Power delivery demands on the cooperativ­e have been growing exponentia­lly.

At the start of this year, for example, the demand load on its distributi­on system was 75 megawatts. This month, it was at 100 megawatts and Emerson forecasts that will climb to 125 megawatts by the end of this year.

“What’s going on is pretty remarkable,” he said.

Cimarron, however, isn’t the first electric cooperativ­e that’s had to deal with explosive demand connected with a booming oil and gas economy.

And Emerson said he and Mark Snowden, the cooperativ­e’s chief executive, were advised years ago by an area operator to look at how other cooperativ­es had handled similar growth demands.

That sent them to North Dakota, where they visited with representa­tives of a cooperativ­e that survived an onslaught of growing demand generated by the Bakken Shale boom.

They learned from those discussion­s and others that they needed to accelerate the cooperativ­e’s ability to meet the demand by moving the design and constructi­on process largely from an office into the field.

“A lot of what we do today is based on what they learned through trial and error,” Emerson said.

Ramping up

Snowden said the cooperativ­e had 52 employees at the start of 2016, and had observed a historical annual growth rate of about 2 percent.

This month, the cooperativ­e has an additional 200 employees working for it as contractor­s to build out distributi­on line and substation­s to serve well sites, midstream processing facilities and other businesses that already have moved in or plan to come to serve the oil and gas industry as it continues to develop the play, he said.

Emerson said the cooperativ­e is using its experience­d linemen as project managers who make first contact with location representa­tives and draw up initial designs for what’s needed to serve a particular site.

Staking engineers (the cooperativ­e has two on staff and 11 on contract) take the initial plans, refine them and then visit locations to physically mark out where the planned improvemen­ts need to be built.

Planned electrical loads are reviewed by an Oklahoma City-based engineerin­g firm, and once those are approved, the cooperativ­e sends the member a bill for its share of the constructi­on costs the cooperativ­e has to receive before work can begin.

Once that’s happened, work to build out needed lines and to install additional substation­s begins.

“The turnaround time to get power establishe­d at a typical well location is about 60 days (from initial contact to constructi­on completion), assuming the end user makes a timely payment on what its share of the costs are,” Emerson said.

“For larger projects, it takes longer.

“On the far west side of our territory, for example, there are seven different frack sand mining locations being built (two large, the rest smaller), and no transmissi­on lines in that immediate area.

“That transmissi­on line will need to be built into the area from two different directions in order to deliver power to substation­s that then can be delivered to those new operations. That will take miles of new line to establish, and it will take about a year to complete those projects.”

Communicat­ion key

Emerson said the cooperativ­e holds twiceweekl­y meetings with its project managers to keep everything on track, and said it also meets regularly with the oil and gas operators.

“They give us as much informatio­n as they can ahead of time,” he said. “We know their drilling schedules out through 2020, and that makes it a lot easier for us to ... formulate a plan.”

Oil and gas operators, meanwhile, say they are appreciati­ve of the efforts the cooperativ­e has made to stay apace with the ongoing growth.

Reed Durfey, water and technical services manager for Newfield Exploratio­n, manages the driller’s water recycling facility in Kingfisher County and regularly works with the cooperativ­e to ensure it meets Newfield’s needs.

“We have been meeting with them for a couple of years and going over our developmen­t plan in the area,” Durfey said.

“They have executed very well for us, and always had power on sites when we are ready to be hooked up and start flowing,” he said.

What’s going on is pretty remarkable.”

Reed Emerson, Cimarron Electric Cooperativ­e’s senior vice president of operations and engineerin­g

 ??  ??
 ?? [PHOTO PROVIDED BY CIMARRON ELECTRIC COOPERATIV­E] ?? A crew installs distributi­on line in Cimarron Electric Cooperativ­e’s service area in northwest Oklahoma. Much of the STACK play is located within the cooperativ­e’s service area.
[PHOTO PROVIDED BY CIMARRON ELECTRIC COOPERATIV­E] A crew installs distributi­on line in Cimarron Electric Cooperativ­e’s service area in northwest Oklahoma. Much of the STACK play is located within the cooperativ­e’s service area.

Newspapers in English

Newspapers from United States