The Palm Beach Post

FPL undergroun­d power cost change approved

- By Susan Salisbury Palm Beach Post Staff Writer

TALLAHASSE­E — A change in how the cost of conversion from overhead to undergroun­d power lines is calculated will save Palm Beach, Palm Beach Shores and four other municipali­ties an estimated $14 million.

Tuesday the Florida Public Service Commission approved a new formula for calculatin­g the cost as requested by Florida Power & Light Co.

Municipali­ties will receive additional credits for the conversion. Previously, municipali­ties paid for the cost of removing overhead facilities that had not been hardened against storms and for the remaining value of the poles and equipment.

Since FPL expects to complete hardening its system in the next five to six years, the company said it will now give the municipali­ties credits for the removal of non-hardened lines and poles.

Juno Beach-based FPL’s storm-hardening costs are recovered from the general body of ratepayers through base rates.

Kevin Donaldson, an FPL attorney, told the commission the change how the costs are calculated will reduce the municipali­ties’ cost and incentiviz­e those who want to switch to undergroun­d systems.

The municipali­ties of Palm Beach, Longboat Key, Palm Beach Shores, Key Biscayne, Sunny Isles Beach and Fort Lauderdale have either begun or are considerin­g converting to undergroun­d lines.

FPL spokesman Bill Orlove said that a breakdown on how much each city would save is not available, but that collective­ly they will pay an estimated $14.2 million less under the new formula.

Palm Beach is in the midst of a nine-year $90 million undergroun­ding project. Work began last summer.

Palm Beach Shores Mayor Myra Koutzen said that in March vot-

ers authorized the town to borrow up to $5.5 million for the project.

“Right now we’re waiting for FPL to complete their plans so we can begin the constructi­on bidding process,” Koutzen said Tuesday, adding that Hurricane Irma caused the project to be delayed.

Schef Wright, a Tallahasse­e attorney representi­ng Palm Beach and Longboat Key, said he supports the new formula which correctly allocates costs where they should be allocated.

Orlove said about 40 percent of FPL’s main power lines are either hardened or undergroun­d.

“Either a hardened line or an undergroun­d line is going to produce the same result. It will enhance reliabilit­y and speed restoratio­n efforts during a severe weather event,” Orlove said.

“A wind-blown event like Hurricane Irma, with trees and other debris going into the line would not affect an undergroun­d line,” he said.

All customers benefit from an undergroun­ding project, FPL said in PSC filings, because there’s a reduced need for storm restoratio­n work in the converted area. That makes crews more available in other areas where lines might be damaged.

Historical­ly, undergroun­d facilities have provided better reliabilit­y than overhead lines and poles.

During Hurricane Matthew in 2016, only 2.2 percent of FPL’s undergroun­d facilities experience­d outages, while 9.4 percent of hardened overhead facilities and 13.8 percent of non-hardened overhead facilities experience­d outages.

Day-to-day reliabilit­y improves with undergroun­d systems as well. A drawback is that locating the cause of an undergroun­d outage and repairing it is generally more difficult and time-consuming than it is for overhead, and the duration of the outage may be longer.

Newspapers in English

Newspapers from United States