The Palm Beach Post

Key design change stymied Fla. bridge’s cost, schedule

- By Jason Dearen and Jennifer Kay

MIAMI — Constructi­on of the pedestrian bridge that collapsed and killed six people in the Miami area was behind schedule and millions over budget, in part because of a key change in the design and placement of one of its support towers.

Documents obtained by The Associated Press through a public-records request show that the Florida Department of Transporta­tion in October 2016 ordered Florida Internatio­nal University and its contractor­s to move one of the bridge’s main support structures 11 feet north to the edge of a canal, widening the gap between the crossing’s end supports and requiring some new structural design.

The span’s signature, 109-foot-tall pylon was to be built atop a footing, or base, at the northern end of the span. In addition to basic support, its design was also aimed at contributi­ng to the aesthetics of the bridge, which itself was touted as an architectu­ral marvel that would span a busy road and canal to connect the rapidly growing university to the nearby community of Sweetwater. In their winning 2015 proposal, designers said the bridge provided “spectacula­r views” for both pedestrian­s using the bridge and drivers passing beneath it. And they added that the tower could serve as a safety feature because it provided an “eagleeyed location” for additional lighting and security cameras.

Videos of the collapse show that the concrete, prefabrica­ted segment of the bridge started crumbling on the same end of the span where the tower redesign occurred, two days after an engineer on the project reported cracks in the same location. The segment that failed had been placed atop the pylon’s footing, and the taller tower section was to be installed later.

Though it is still unclear if the design change played a role in the failure, emails between the school, contractor­s, officials with the city of Sweetwater and permitting agencies show a project that ended up behind schedule, which had officials worried that further delays could jeopardize millions in federal Department of Transporta­tion funds.

When the bridge collapsed, the project was already running about $2.6 million over its $9.4 million initial budget, cost-tracking documents from February show. Originally scheduled to be completed in July, the finish date had been pushed back to January 2019.

Difficulti­es began in late 2016, when the Florida Department of Transporta­tion emailed project officials saying they needed to move the bridge’s signature pylon to allow for future widening of the road, according to the documents. The tower was to be located on the north side between the road and the canal, and was designed to have cables connecting it to the structure below.

“The first option being entertaine­d is providing these extra travel lane (sic) on the north side of SW 8th St.,” wrote Alfred Reyna, a transporta­tion department employee working on the bridge project. “This first option places the current location of the pylon in conflict with the extra travel lane and would require bridge design modificati­ons.”

After weeks of back and forth, it was decided to move the pylon 11 feet to the north, sitting near the edge of the canal. According to documents, initial costs for the new design were $204,540, with another $402,723 for constructi­on changes. The final cost of the change was not divulged in the documents.

“The city attorney is advising us not to speak about anything to do with the bridge,” said Sandra Antonio, a spokeswoma­n for the city of Sweetwater, which was working on the bridge project with FIU. The tower was to be located on the Sweetwater side of the project.

 ?? MATIAS J. OCNER / MIAMI HERALD ?? When the bridge collapsed, the project was about $2.6 million over its initial budget, cost-tracking documents from February show.
MATIAS J. OCNER / MIAMI HERALD When the bridge collapsed, the project was about $2.6 million over its initial budget, cost-tracking documents from February show.

Newspapers in English

Newspapers from United States