The Reporter (Lansdale, PA)

Rittenhous­e Road repairs nearly done

Bridge was damaged twice in 2019

- By Dan Sokil dsokil@21st-centurymed­ia.com @Dansokil on Twitter

A bridge that’s been damaged for nearly a year could soon be ready to handle traffic again.

Township officials gave an update Wednesday night on repairs, now nearly complete, to a damaged culvert on Rittenhous­e Road.

“The project is progressin­g nicely. The culvert is installed, the wing walls are in, and you can see the precast slab culvert and the wing walls,” said supervisor Rich Marino.

In July 2019 the bridge was damaged by an auto accident, causing a closure for two weeks as the damage was evaluated. Later that month Rittenhous­e Road was temporaril­y changed to one-way only when the bridge reopened, and the one-way was made permanent on Sept. 11, days before a second accident on Sept. 20 did further damage requiring a closure.

Last October, the township’s engineer said repairs might be finished faster under an emergency repair classifica­tion, and in November the board bid out the purchase of a new prefabrica­ted culvert to save time over having one custom-made. Emergency state permits were finalized in December, in January the board bought the prefabrica­ted culvert for roughly $14,000, and in February awarded a $104,000 contract for the constructi­on. In March the engineer said work was ready to begin pending permission from the state and work by the North Penn Water Authority to modify a 16-inch water main close to the culvert, and in April the latest

update was that the culvert would be on site and ready for installati­on in early May once state limits on constructi­on activity were lifted. Staff have said they are pursing the drivers involved in the accident for compensati­on to cover the cost of the repairs, and that the one-way or two-way traffic flow will be part of a traffic study once the road reopens and coronaviru­srelated travel restrictio­ns are lifted.Marino and township Engineer Tom Zarko gave an update Wednesday night, as part of their report on recent Public Works-related activities in the township. As they spoke, they pointed out details on photos Marino took at the site on the way to the supervisor­s meeting, with the photos projected in the township building meeting room and on an online video stream. As of Wednesday night, timbers could be seen sticking out above the precast culvert, with newly settled stone below and gravel atop the culvert.

“They anticipate they will be paving either Friday or Monday,” Zarko said.

Final inspection of the newly repaved roadway could be done as soon as the end of next week, on or around June 19, with the reopening possible shortly thereafter and formal announceme­nts from the township once it happens, Zarko and Marino said.

“The project is coming along nicely,” Marino said.

Towamencin’s supervisor­s next meet at 7:30 p.m. on June 24; for more informatio­n visit www.Towamencin.org.

 ?? PHOTO COURTESY OF RICH MARINO ?? A newly installed prefabrica­ted culvert is seen being installed on Rittenhous­e Road in Towamencin, where a previous culvert was damaged in July 2019.
PHOTO COURTESY OF RICH MARINO A newly installed prefabrica­ted culvert is seen being installed on Rittenhous­e Road in Towamencin, where a previous culvert was damaged in July 2019.
 ??  ??

Newspapers in English

Newspapers from United States