The Sentinel-Record

Billions down the drain as new nuclear plants scrapped

- SEANNA ADCOX The Associated Press

COLUMBIA, S.C. — Billions of dollars spent on two new nuclear reactors in South Carolina went up in smoke Monday when the owners nixed plans to finish them after years of delays and cost overruns, dealing a severe blow to the industry’s future.

The reactors were set to be among the first built in the U.S. in decades. While the decision will save customers billions in additional costs, customers of the two utilities — Santee Cooper and South Carolina Electric & Gas — may get little to nothing refunded of the billions they’ve already paid for the now-abandoned project.

“I’m disappoint­ed today not just for Santee Cooper and its customers but for our country and the industry as a whole,” said Santee Cooper CEO Lonnie Carter. “If you really believe we need to reduce carbon, this was the way to do it.”

Energy demands are far less than the utility’s pre-Great Recession projection­s that factored into the initial decision to build.

But Monday’s decision may eventually result in the utility putting a coalfired unit idled earlier this year back in operation. Another option for supplying power needs in the decades to come include building a natural gas unit.

“Absolutely, this pushes us back to more carbon, whether it’s natural gas or coal,” Carter said.

Santee Cooper’s board said the decision to end constructi­on will save customers an estimated $7 billion. The utility had already spent about $5 billion for its

45 percent share of the project, and completing it would have cost an additional

$8 billion, plus $3.4 billion in interest. “I’m not celebratin­g,” said Tom Clements of Friends of the Earth, which has questioned the project from the outset. “This is a sad day for South Carolina. So much money has been wasted. Ratepayers are losers any way you take it.”

He said the group will work to “get to the bottom line of how this happened, who’s responsibl­e” and what that means for customers.

Gov. Henry McMaster called for legislator­s to hold hearings to get customers’ questions answered.

The project has been shrouded in doubt since earlier this year, when primary contractor Westinghou­se filed for bankruptcy protection.

The utilities have since determined the project likely wouldn’t have been finished until 2024. Under a timeline adopted in 2012, the first reactor was supposed to be operationa­l earlier this year. Westinghou­se hasn’t been forthright since, according to Santee Cooper.

South Carolina Electric & Gas, which owns 55 percent, announced its plans shortly after Santee Cooper’s unanimous vote. SCANA, SCE&G’s parent company, will seek approval from regulators Tuesday about their abandonmen­t plans.

Under the approved Santee Cooper resolution, all work will end within six months. How quickly within that timeframe workers at the site will lose their jobs is uncertain.

About 5,000 people are employed at the site by contractor­s and subcontrac­tors. SCE&G employs an additional 600 workers for the project, according to the utility.

The utilities announced last week that Westinghou­se’s parent company, Toshiba Corp., agreed to jointly pay them $2.2 billion regardless of whether the reactors are ever completed.

Santee Cooper will use its $1 billion share from Toshiba — to be collected between October and 2022 — to lower customers’ future costs, Carter said. But it’s unclear if that will translate to lower bills. Rates are rising due to environmen­tal projects, and the money could offset either those costs or debt, Carter said.

SCE&G will use the money to ensure customers see no increase in their bills for at least the next several years, SCANA CEO Kevin Marsh told investors Monday afternoon.

But another unknown is whether Toshiba will actually pay. In May, the Tokyo-based company projected a 1.01 trillion yen ($9.2 billion) loss for the fiscal year that ended in March.

The reactors were planned for the V.C. Summer Nuclear Station north of Columbia. Constructi­on contracts with Westinghou­se were signed in 2008, and the project was so far about one-third completed.

Environmen­tal groups have called on state regulators to order SCE&G to abandon the projects. They also want customers to be refunded at least some of the billions they’d paid upfront through rates that have increased yearly since 2009. A hearing on that request is set for October.

A 2007 state law allows electric utilities to collect money from customers to finance a project before it generates power. Constructi­on now accounts for 18 percent of the electric bills of SCE&G’s residentia­l customers.

 ?? The Associated Press ?? NUCLEAR PROJECT: This April 9, 2012, file photo shows constructi­on well underway for two new nuclear reactors at the V.C. Summer Nuclear Station in Jenkinsvil­le, S.C. South Carolina’s state-owned public utility has voted to stop constructi­on on two...
The Associated Press NUCLEAR PROJECT: This April 9, 2012, file photo shows constructi­on well underway for two new nuclear reactors at the V.C. Summer Nuclear Station in Jenkinsvil­le, S.C. South Carolina’s state-owned public utility has voted to stop constructi­on on two...

Newspapers in English

Newspapers from United States