The Sentinel-Record

City awaits clearance on Majestic

- DAVID SHOWERS

It took three months to raze the Majestic Hotel’s “red brick” building, Lanai Tower and Lanai Suites, but obtaining the environmen­tal clearance that will inform how the property is developed has been a slower process.

The city’s demolition contractor turned the site over to it in mid-November. Since then, the city has been waiting for the Arkansas Department of Environmen­tal Quality to conclude the phase two comprehens­ive site assessment. Assistant City Manager/ City Clerk Lance Spicer said last week he expects to hear from ADEQ soon.

ADEQ contractor FTN Associates concluded its field work last month. Samples collected from eight subsurface and groundwate­r borings have been

submitted to the secondary contractor, Center for Toxicology & Environmen­tal Health LLC, Spicer said.

The latter is preparing a human health risk assessment based on what it finds in the samples. The assessment will determine the necessary measures for obtaining an environmen­tal clearance for the property.

“In the grand scheme of things in a phase two, they’re in the last part of it,” Spicer said. “Things are moving along, and we expect to have a report from ADEQ relatively soon. Whenever you deal with environmen­tal issues, the regulators are very careful and methodical as they move through the closeout process.”

Phase two is an analysis of the recognized environmen­tal conditions identified during the initial site assessment in April 2014. Most of its findings related to the concrete fuel bunker on the north end of the “yellow brick” building parcel. Spicer said correspond­ence the previous owner provided the city indicated steps had been taken more than a decade ago to mitigate it.

“We expect phase two to tell us the fuel bunker could have some possible small-scale leaking that will require us to remove the bunker and excavate a little of the area around it,” Spicer said, explaining that the bunker was used to hold heating oil for the “yellow brick” building that was demolished after a February 2014 fire.

“The levels of contaminat­ion, I wouldn’t be shocked if they’re very low. It’s a small bunker that was remediated in the mid-2000s.”

The city’s enrollment of the property in ADEQ’s brownfield assistance program in 2014 made ADEQ responsibl­e for the cost and administra­tion of the site assessment.

“Instead of having to contract with FTN on our own, ADEQ is contractin­g with FTN on our behalf,” Spicer said. “It’s a big help. It’s a relatively expensive process to go through on your own, but with the state and federal assistance it really does help out.”

The city budgeted $50,000 this year toward the redevelopm­ent of the property. Part of that money will pay for the city’s participat­ion in Kansas State University’s Targeted Assistance to Brownfield­s program, which helps communitie­s find new purposes for properties where previous developmen­ts were located.

Public input received during open meetings facilitate­d by the TAB program will be distilled into visual form by the University of Arkansas’ Fay Jones School of Architectu­re and Design. Its students will create architectu­ral renderings that make prospectiv­e plans more tangible.

“We’re in hurry up and wait mode, but once we get the phase two report and know what direction we can take, we’ll be well positioned to move those meetings along relatively quickly,” Spicer said.

The land value of the four parcels that constitute the 5-acre Majestic property has increased by more than 50 percent since the city acquired it in 2015, according to updated values posted after the conclusion of this year’s countywide reappraisa­l. The land is appraised at

$1,337,650, according to Garland County’s contract appraisal service, up from

$884,350.

The city purchased the property from Park Residences Developmen­t for

$672,782 and spent $1.3 million demolishin­g and removing four structures from it.

 ?? The Sentinel-Record/Grace Brown ?? MAJESTIC LOT: The city is waiting for the Arkansas Department of Environmen­tal Quality to conclude the phase two comprehens­ive site assessment of the vacant lot where the Majestic Hotel once stood at the north end of downtown.
The Sentinel-Record/Grace Brown MAJESTIC LOT: The city is waiting for the Arkansas Department of Environmen­tal Quality to conclude the phase two comprehens­ive site assessment of the vacant lot where the Majestic Hotel once stood at the north end of downtown.