The Trentonian (Trenton, NJ)

APNewsBrea­k: Key design change stymied bridge cost, schedule

- By Jason Dearen and Jennifer Kay

MIAMI » Constructi­on of the pedestrian bridge that collapsed and killed six people in the Miami area was behind schedule and millions over budget, in part because of a key change in the design and placement of one of its support towers.

Documents obtained by The Associated Press through a public-records request show that the Florida Department of Transporta­tion in October 2016 advised Florida Internatio­nal University and its contractor­s to move one of the bridge’s main support structures 11 feet (3 meters) north to the edge of a canal, widening the gap between the crossing’s end supports and requiring some new structural design.

The span’s signature, 109-foot-tall (33-meter-tall) pylon was to be built atop a base at the span’s northern end. It was designed for basic support and to contribute to the aesthetics of the bridge, which was touted as an architectu­ral marvel that would connect the rapidly growing university to the nearby community of Sweetwater. In their winning 2015 proposal, designers said the bridge provided “spectacula­r views” for both pedestrian­s using the bridge and drivers passing beneath it. They added that the tower could serve as a safety feature because it would have an “eagle-eyed location” for additional lighting and security cameras.

Videos of the collapse show that the concrete, prefabrica­ted segment of the bridge started crumbling on the same end of the span where the tower redesign occurred, two days after an engineer on the project reported cracks in the same location. The segment that failed had been placed atop the pylon’s footing, and the taller tower section was to be installed later.

U.S. Transporta­tion Secretary Elaine Chao has ordered her department’s inspector general to conduct an audit of the bridge, according to a news release Tuesday from the U.S. Department of Transporta­tion. The agency awarded millions of dollars to the project.

It is still unclear if the design change contribute­d to the failure. But emails between the school, contractor­s, Sweetwater city officials and permitting agencies show a project that was behind schedule, which had officials worried that further delays could jeopardize the federal funding.

When the bridge collapsed, the project was already running about $2.6 million over its $9.4 million initial budget, cost-tracking documents from February show. Originally scheduled to be completed in July, the finish date had been pushed back to January 2019.

Difficulti­es began in late 2016, when the Florida Department of Transporta­tion emailed project officials saying they wanted more room to allow for future widening of the U.S. highway under the bridge, according to the documents. The new position of the tower would be on the north side between the road and the canal.

“This ... places the current location of the pylon in conflict with the extra travel lane and would require bridge design modificati­ons,” Alfred Reyna, a transporta­tion department employee working on the bridge project, wrote in an email.

After weeks of back and forth, it was decided to move the pylon 11 feet to the north, sitting near the edge of the canal. According to documents, initial costs for the new design were $204,540, with another $402,723 for constructi­on changes. The final cost was not divulged.

“The city attorney is advising us not to speak about anything to do with the bridge,” said Sandra Antonio, a spokeswoma­n for the city of Sweetwater, which was working with FIU. The tower was to be located on the Sweetwater side.

Don Silver, a spokesman for Munilla Constructi­on Management, or MCM, the Miami-based constructi­on management firm that won the bridge contract, said the National Transporta­tion Safety Board forbade engineers or contractor­s from talking about the project pending its investigat­ion. MCM collaborat­ed with Tallahasse­e-based FIGG Bridge Design on the bridge project, which also declined comment.

A spokeswoma­n for FIU, Maydel Santana, declined comment on the pylon redesign, but did confirm Tuesday that the bridge was expected to be completed early in 2019 and the grant ran out on Sept. 30, 2019. She also said the school was cooperatin­g with the NTSB’s investigat­ion.

While the NTSB probe has just begun, multiple engineers who reviewed the documents obtained by the AP said moving the tower after the bridge’s initial design invited errors.

 ??  ??
 ??  ??

Newspapers in English

Newspapers from United States