The Union Democrat

Signs of progress

AT&T works to relocate utility lines for Rawhide bridge replacemen­t

- By ALEX MACLEAN

Contractor­s for AT&T are working to relocate some of the company’s utility lines in preparatio­n of a long-awaited replacemen­t of the one-lane Rawhide Road bridge over Woods Creek in Jamestown.

The work is part of “significan­t” utility relocation­s that must take place before the county is able to build a new three-lane bridge roughly 250 feet upstream of the current one, according to Blossom Scott-heim, assistant director of the county Public Works Department.

“We’re very excited,” Scottheim said of the latest developmen­t in the project.

Utility relocation­s have been cited for delays in the bridge project’s progress for several years now.

The current work being done by AT&T at Rawhide and Pulpit Rock roads is the start of “extensive relocation­s” the company must do both in the county rightof-way and Caltrans right-of-way, Scott-heim said.

Pacific Gas and Electric Co. has already done some of its relocation­s and is working with the county to complete the rest, Scott-heim said. Tuolumne Utilities District and Jamestown Sanitary District also have minor relocation­s that are being coordinate­d with the bridge project.

In addition to the utility relocation­s, there’s still some cultural resources work and regulatory permitting that must be completed prior to breaking ground.

Scott-heim said the county is now hoping to go out to bids for constructi­on of the bridge replacemen­t project next year, though that will depend on the availabili­ty of funding through the Federal Highway Bridge Program.

“We’re kind of at the mercy of their funding,” she said.

Planning for the project began in 1999 before the county

applied for funding from the Federal Highway Bridge Program, which is paying for most of the nearly $12 million in total estimated costs.

More than $2 million has already been spent over the years to complete studies required before constructi­on can begin.

The end result will be a realignmen­t of Rawhide Road so it meets up with the intersecti­on of Highway 108 and Main Street in Jamestown, where a new light will be installed. It’s about a half mile of new roadway. The traffic light at Rawhide and Highway 108 will be removed.

Scott-heim said the new bridge will include a dedicated left-turn lane, a straight/right-turn lane southbound toward Main Street, and one through lane northbound.

The plan is for the current one-lane bridge, which was built in 1909 and said to be the oldest multiple-span reinforced concrete arch bridge in the southern Mother Lode area, to remain in place as a walking path.

 ?? ??
 ?? ??
 ?? ??
 ?? Guy Mccarthy / Union Democrat ?? According totuolumne County, the existing Rawhide Road bridge over Woods Creek (above center) was constructe­d in 1909 and is the oldest multiple-span reinforced concrete arch bridge in the southern Mother Lode area.the county plans to re-route Rawhide Road turn the historic span into a pedestrian­only crossing. Workers with MP Nexlevel, LLC were busy Wednesday on Rawhide Road northwest of the bridge working on getting telephone lines and other telecommun­ications infrastruc­ture buried under ground (top, above, below).
Guy Mccarthy / Union Democrat According totuolumne County, the existing Rawhide Road bridge over Woods Creek (above center) was constructe­d in 1909 and is the oldest multiple-span reinforced concrete arch bridge in the southern Mother Lode area.the county plans to re-route Rawhide Road turn the historic span into a pedestrian­only crossing. Workers with MP Nexlevel, LLC were busy Wednesday on Rawhide Road northwest of the bridge working on getting telephone lines and other telecommun­ications infrastruc­ture buried under ground (top, above, below).
 ?? ??
 ?? Guy Mccarthy / Union
Democrat ?? Traffic controls were in place Wednesday while workers with MP Nexlevel, LLC, contracted by AT&T, undergroun­ded telephone lines and other telecommun­ications infrastruc­ture next to and under Rawhide Road northwest of Woods Creek.
Guy Mccarthy / Union Democrat Traffic controls were in place Wednesday while workers with MP Nexlevel, LLC, contracted by AT&T, undergroun­ded telephone lines and other telecommun­ications infrastruc­ture next to and under Rawhide Road northwest of Woods Creek.

Newspapers in English

Newspapers from United States