Yuma Sun

• Road Report/

-

16th Street and 4th Avenue

Starting Monday evening, work crews will apply thermoplas­tic lane striping throughout the 16th Street and 4th Avenue intersecti­on project area, requiring lane closures in the areas where work will be done. Isolated lane restrictio­ns in and near the 16th Street and 4th Avenue intersecti­on are possible to accommodat­e work on walls adjacent to the roadways.

22nd Street, 4th Avenue to Avenue A

Starting Monday, a contractor working for the city will begin making improvemen­ts to 22nd Street between 4th Avenue and Avenue A. Work will include replacing the roadway itself, as well as replacing 1950’s-era water pipes, and improving curbs, gutters and sidewalks.The first phase of this 90-day project will take place between 4th Avenue and the eastern drive to the U.S. Post Office. To access the post office, drivers may take 22nd Street from 8th Avenue, and follow the detour signs to enter the parking lot through the western driveway. Cars will be able to exit the post office via southbound 4th Avenue.

16th Street, Maple to 1st Avenue

Turn lane work will take place on westbound 16th Street between Maple Avenue and 1st Avenue. Westbound 16th Street will be reduced to one lane in the work zone. Eastbound traffic should not be affected. Work is expected to finish in early June, taking a total of about three weeks.

I-8, Giss Parkway — ADOT

The westbound off and on ramps at I-8 and Giss Parkway are closed through mid-June. The Arizona Department of Transporta­tion (ADOT) will maintain twoway traffic on Giss Parkway and access to businesses in the work zone.

This is part of an ADOT project to improve the interchang­e area of westbound Interstate 8 and Giss Parkway, and will take approximat­ely seven months to complete. The $1.8 million project will consist of the constructi­on of a twolane roundabout at the interchang­e to accommodat­e commercial trucks and other large vehicles. Work will also improve drainage, intersecti­on lighting, signage and lane striping. Drivers will be asked to use alternate routes, including the 16th Street exit. The speed limit in the work zone will be reduced. Drivers should watch for constructi­on personnel and equipment, and obey all posted speed limits and signs.

Pacific Avenue, near 24th Street

Yuma County is currently doing a milling and filling roadway project, replacing 2-1/2 inches of pavement along Pacific Avenue between 24th Street and the Union Pacific Railroad bridge just north of 24th Street. Traffic is currently reduced to one lane in each direction along Pacific Avenue in both directions. The speed limit in the work zone is reduced to 25 mph while work is underway.

18th Street, Arizona Avenue

A lane will be closed on 18th Street near its intersecti­on with Arizona Avenue for a 60-day project that requires access to a manhole. Work is to finish by mid-July. Signs will be posted to direct traffic to keep right when traveling in either direction on 18th Street near the area.

16th Street, between avenues B and C

A city of Yuma xeriscape project is currently underway, aiming to improve Rancho Viejo II subdivisio­n’s basin and irrigation system which is located near the south side of 16th Street between avenues B and C. Work is to be completed by mid-June and is not expected to have any major traffic implicatio­ns, aside from some traffic control at the time when trucks arrive to deliver material needed for the project.

Avenue 3E, 40th Street

A trenching and manhole installati­on project near Avenue 3E and 40th Street will require the lane closure of Avenue 3E’s northbound lane in the area. Access to businesses in the area will be maintained. The Marine Corps Air Station Yuma main gate will be closed for the duration of the project.

1st Avenue, 24th-26th streets

Crews have begun a project to relocate a waterline along 1st Avenue and Madison Avenue, between 24th and 26th streets. Additional­ly, they will be replacing pavement along 1st Avenue and replacing four sewer manholes in that area. Work is scheduled to be complete by July 4.

18th Street, 4th-6th avenues

A project to install a bond wire on 18th Street between 4th and 6th avenues will require a road closure. Work will take a total of one day, and will be scheduled sometime before May 27. During the one-day project, there will be a partial closure of 18th Street. Additional­ly, 5th Avenue will be closed to through traffic between 17th and 18th Street. Detours include 4th and 6th avenues.

Drivers will not be permitted to use the nearby alleyways that are located between 4th and 5th avenues and between 5th and 6th avenues as a detour.

Magnolia Avenue, 3rd Street to Colorado Street

A partial closure along Magnolia Avenue will be needed for shoulder work along the roadway from 3rd Street to Colorado Street, and then east to 9th Avenue, as crews access a manhole to pull a fiber cable through an existing conduit. Work is to be completed by Friday. Traffic control signs will be posted in the work zones as crews move throughout the area. Additional­ly, there will be no parking permitted along some sidewalks near the work zone while crews are in the area.

Araby Road, I-8 waterline relocation

A project to relocate a waterline on Araby Road near its intersecti­on with Interstate 8 is underway with estimated completion in June. Drivers are urged to avoid the area if possible. This work precedes a series of roundabout installati­ons ADOT has planned for this vicinity.

8th Street, Castle Dome and Pacific Avenue

8th Street is closed between Castle Dome and Pacific Avenue. Pacific Avenue is closed to through traffic north of 12th Street, and closed to all traffic north of 8th Street. Roadway, water and sewer work is being done in conjunctio­n with the Pacific Avenue Athletic Complex. Detour by using 12th Street between Pacific and Castle Dome Avenue. The project is anticipate­d to be complete in late summer.

Avenue 3E/U.S. 95

A nine-month project to widen and improve both U.S. 95 and Avenue 3E is currently underway.

Highway 95 is reduced to one lane of traffic in each direction from Avenue 3E to Araby Road (a stretch of approximat­ely 3.5 miles) as part of the constructi­on for this project. The speed limit in the area will be reduced to 25 mph. The $3.2 million project will widen both roads to five lanes and to include a turn lane. Work will take place on Avenue 3E from north of the Interstate 8 interchang­e to past the U.S. 95 intersecti­on, as well as on U.S. 95 from about 500 feet west of the Avenue 3E intersecti­on to just past the Araby Road intersecti­on. Both roads are expected to remain open with lane restrictio­ns in place while the project is underway. Drivers are asked to find alternate routes to avoid potential delays. Arizona Department of Transporta­tion (ADOT) will maintain access to businesses in the work zone and keep both roadways open during constructi­on. The project is scheduled to be completed by August.

U.S. 95 at Fortuna Wash — ADOT

Work is underway on the bridge on U.S. Highway 95 spanning Fortuna Wash northeast of Yuma and is expected to be completed by next winter. The bridge is going in at milepost 34, approximat­ely 12 miles northeast of Yuma and 10 miles south of the turnoff (Imperial Dam Road) to Yuma Proving Ground. Crews are scheduled to work weekdays between 6 a.m. and 4 p.m. Motorists should allow extra travel time as lane restrictio­ns will be in place and flaggers will occasional­ly need to alternate traffic through the work zone.

20th Street, Arizona to Walnut avenues

As part of a project to replace a steel main line near the northwest corner of Arizona Avenue and 20th Street, additional traffic control will be in place. This includes a lane shift for southbound traffic approachin­g the intersecti­on along Arizona Avenue and a separate full closure of Arizona Avenue when necessary. Additional­ly, 20th Street will be closed between Arizona Avenue and Walnut Avenue to all traffic for a portion of the project.

I-8 west of 4th Avenue — Caltrans (updated)

Caltrans crews continue to work on the reconstruc­tion of Interstate 8 in Imperial County, west of Yuma. Caltrans closed westbound Interstate 8 ramps on May 8 at Algodones Road/ State Route 186 (SR-186) due to ongoing constructi­on. Signs will be in place to alert motorists to the ramp closures and alternate routes. The closures and detours will be in place through August. Crews continue work on I-8 from SR-111 to the California/ Arizona border in Imperial County. Lane closures and traffic closures along I-8 may cause delays.

The I-8 corridor is a major pavement rehabilita­tion project consisting of five segments that will construct Continuous­ly Reinforced Concrete Pavement (CRCP) over 48 miles on Interstate 8 in Imperial County. The work will result in a long-lasting superior roadway, capable of withstandi­ng the heaviest traffic loads. Constructi­on began in 2016 on three of the five segments. Work will be completed by 2019.

City street maintenanc­e

Asphalt maintenanc­e crews will conduct operations Monday through Friday in various locations as needed:

• 40th Street, from Avenue 4E to Avenue 6E (crack seal)

• 32nd Street, from West Catalina Drive to South Arizona Avenue (crack seal)

• South Avenue A’s northbound lane, from 32nd to 24th streets (grinding)

• 32nd Street, from West Catalina Drive to South Pacific Avenue (grinding)

Newspapers in English

Newspapers from United States