- FROM CITY OF YUMA

22nd Street, 4th Avenue to Avenue A

There will be a complete closure along the portion of 22nd Street between 8th Avenue and Avenue A for the next several weeks. Drivers are politely asked to plan ahead and detour using 24th Street.

20th Street, Avenue 10E

Crews will be working in the area of 28th Street’s intersecti­on with Avenue 10E to install a feeder line undergroun­d and then install a conduit in the intersecti­on. Work will require closed shoulders on both 20th Street and Avenue 10E near the vicinity of their intersecti­on. Flaggers will be directing traffic through the work zone. The project is expected to take a total of 12 days and will finish by Aug. 4.

40th Street Pathway, near 32nd Street

Crews will install a pedestrian refuge near 32nd Street and the East Main Canal crossing next week, requiring lane shifts and a reduction of traffic to one lane in each direction in the work zone.

I-8, Giss Parkway — ADOT

The Arizona Department of Transporta­tion (ADOT) will maintain two-way traffic on Giss Parkway and access to businesses near the work zone. The westbound off- and on-ramps at I-8 and Giss Parkway remain closed through mid-August.

This is part of an ADOT project to improve the interchang­e area of westbound Interstate 8 and Giss Parkway, and will take approximat­ely seven months to complete. The $1.8 million project will consist of the constructi­on of a two-lane roundabout at the interchang­e to accommodat­e commercial trucks and other large vehicles. Work will also improve drainage, intersecti­on lighting, signage and lane striping. Drivers will be asked to use alternate routes, including the 16th Street exit. The speed limit in the work zone will be reduced. Drivers should watch for constructi­on personnel and equipment, and obey all posted speed limits and signs. I-8, Araby Road — ADOT

ADOT will also be relocating telecommun­ication lines on Araby Road, Gila Ridge Road and I-8. The following restrictio­ns will be in place around the clock through today: • The westbound I-8 on-ramp and eastbound I-8 off-ramp at Araby Road will be closed. A rightturn only restrictio­n will be in place from westbound I-8 to northbound Araby Road. Drivers are asked to consider using Avenue 3E or Avenue 8-1/2E instead. • Araby Road will be narrowed

to one 11-foot lane in each direction from the north side of Interstate 8 to the south side of Interstate 8 and the speed limit will be reduced to 25 mph. Drivers can use Avenue 3E or Avenue 8-1/2E as a detour. • Gila Ridge Road will be closed in both directions just south of Araby Road at the Tanimura and Antle Produce building; however, access to Tanimura and Antle will remain open on the west side of the building. Plan for heavy traffic and allow extra time.

8th Street, Castle Dome and Pacific Avenue

8th Street is closed between Castle Dome and Pacific Avenue. Pacific Avenue is closed to through traffic north of 12th Street, and closed to all traffic north of 8th Street. Roadway, water and sewer work is being done in conjunctio­n with the Pacific Avenue Athletic Complex. Detour by using 12th Street between Pacific and Castle Dome Avenue. The project is anticipate­d to be complete in late summer.

Avenue 3E/U.S. 95

A nine-month project to widen and improve both U.S. 95 and Avenue 3E is currently underway.

Highway 95 is reduced to one lane of traffic in each direction from Avenue 3E to Araby Road (a stretch of approximat­ely 3.5 miles) as part of the constructi­on for this project. The speed limit in the area will be reduced to 25 mph. The $3.2 million project will widen both roads to five lanes and to include a turn lane. Work will take place on Avenue 3E from north of the Interstate 8 interchang­e to past the U.S. 95 intersecti­on, as well as on U.S. 95 from about 500 feet west of the Avenue 3E intersecti­on to just past the Araby Road intersecti­on. Both roads are expected to remain open with lane restrictio­ns in place while the project is underway. Drivers are asked to find alternate routes to avoid potential delays. The Arizona Department of Transporta­tion (ADOT) will maintain access to businesses in the work zone and keep both roadways open during constructi­on. The project is scheduled to be completed by August.

I-8 west of 4th Avenue — Caltrans

Caltrans crews continue to work on the reconstruc­tion of Interstate 8 in Imperial County, west of Yuma. Caltrans have closed westbound Interstate 8 ramps at Algodones Road/State Route 186 (SR-186) due to ongoing constructi­on. Signs will be in place to alert motorists to the ramp closures and alternate routes. The closures and detours will be in place through August. Crews continue work on I-8 from SR-111 to the California/Arizona border in Imperial County. Lane closures and traffic closures along I-8 may cause delays.

The I-8 Corridor is a major pavement rehabilita­tion project consisting of five segments that will construct Continuous­ly Reinforced Concrete Pavement (CRCP) over 48 miles on Interstate 8 in Imperial County. The work will result in a long-lasting superior roadway, capable of withstandi­ng the heaviest traffic loads. Constructi­on began in 2016 on three of the five segments. Work will be completed by 2019.

City street maintenanc­e

Asphalt maintenanc­e crews will conduct operations Monday through Friday in various locations as needed in the following locations: • 32nd Street from Catalina Drive to Arizona Avenue (crack seal) • 32nd Street from Winsor Avenue to Pacific Avenue (crack seal)

During this crack seal project, the speed limit in the sections of 32nd Street listed above will be reduced from 45 mph to 25 mph. Traffic control signs will be in place.

• 32nd Street from Pacific Avenue to Arizona Avenue (grinding)

• 32nd Street from Fortuna Avenue to Pacific Avenue (grinding)

 ??  ??