City of Yuma Road Report
A weekly list of city projects or encroachment permits issued by the City of Yuma affecting busy streets.
CITY PROJECTS 1st Avenue reconstruction project
A project is underway on 1st Avenue between 16th Street and Orange Avenue to repair underground water/sewer infrastructure, to upgrade sidewalks and driveways, and to improve surface pavement. Right now, 16th Street is reduced to one lane in each direction, with left turns prohibited, near 1st Avenue, and 1st Avenue is fully closed from 13th Street to 16th Street.
Sewer work in 16th Street has been completed and the contractor is now working to restore the pavement. A new asphalt surface course will be installed between Maple Avenue and 2nd Avenue. Lane restrictions on 16th Street are anticipated to continue through the third week in July.
City Street Maintenance
Street maintenance operations for July 8-12 will take place in the following locations. Crack seal operations: • Park West subdivision • Rancho Sereno • Sunset Mesa Grinding operations: • Araby Blaisdell Road east of Avenue 9E • Estancia area • 48th Street (County 13th Street) from Avenue 7¾ E to Avenue 8E
• 56th Street (County 14th Street) from Avenue 7E to Avenue 8E Concrete sidewalk repairs: Public Works maintenance crews will be working on sidewalk repairs in the Rancho Sereno subdivision and 26th Place between Arizona Avemue and Pacific Avenue. The recent heat has caused sidewalks to buckle upward, creating a tripping hazard. Pedestrian crosswalk repairs: While students are off for summer break, Public Works will perform crosswalk maintenance around school zones. The goal is to ensure all designated crosswalks are well marked for the upcoming school year. The following schools will be reviewed and repaired: Pecan Grove, Carver Elementary, Yuma High School, H.L. Suverkrup, Rancho Viejo, Ronald Reagan and O.C. Johnson.
OTHER UTILITY PROJECTS, ENCROACHMENT PERMITS 8th Street, Avenue C to Avenue D — Yuma County
Yuma County is reconstructing and widening 8th Street between Avenue C and Avenue D. The work includes widening the roadway to a 5-lane section with sidewalks, streetlights and drainage improvements. Currently, there is shoulder work taking place on the north side of the roadway through December. In the future the roadway will be closed to through traffic, but access will be maintained to local homes and businesses. Completion of the collaborative project is anticipated by early November.
Pacific Avenue and 16th Street
Crews will conduct underground drilling and install fiber from an existing pole at Pacific Avenue and 16th Street. Lane restrictions will be in place at various legs of the intersection as required. Work will take place through July 15.
32nd Street, 8th Avenue (APS)
The right eastbound lane of 32nd Street will be closed from 8th Avenue to just west of 4th Avenue for APS pole maintenance. Work will take place for a single day between July 8-12.
20th Street, Avenue B to Naples Avenue
20th Street will be closed from Avenue B to Naples Avenue July 1-5 between 5:30 a.m. and 6 p.m. on weekdays for underground work. Access to the restaurant and ice cream store at the southwest corner will come from Avenue B. Work will resume for one day at some point during the week of July 8 for asphalt paving.
Work continues on Avenue B between 16th Street and 20th Street, as part of the same project (see below). Avenue B will have reduced lanes/lane shifts.
Avenue C, 12th-14th streets (APS)
The right northbound lane of Avenue C will be closed between 12th Place and 14th Street for APS pole maintenance. Work will take place for a single day between July 8-12.
Avenue B, 16th Street to 20th Street (SW Gas)
A contractor working for Southwest Gas will replace a gas line on Avenue B from 16th Street to 20th Street, with work in cross streets 24th Street, 25th Street, 26th Street and 32nd Street. Project will run the end of September. Expect lane closures on Avenue B and some possible turn restrictions.
3rd Street, 13th-25th avenues (CenturyLink)
Telephone cable maintenance will cause lane narrowing on 3rd Street between 13th Avenue and 25th Avenue. Work will conclude no later than mid-August.
Avenue 2-1/2E at 24th St. (APS)
APS will replace an underground line along 24th Street through the end of August. Work will take place on the eastbound shoulder of 24th Street; while lane closures are not planned, motorists are asked to obey speed limit in the work zone. Avenue 2-1/2E will have a southbound lane closure south of 24th.
Avenue 9E, 24th Street to North Frontage
Avenue 9E will have narrowed lanes and reduced speed limit between 24th Street and North Frontage Road for bike lane designation, signage installation and lane striping. The two-month project is expected to be complete in mid-July.
24th St. at Avenue 9E (SW Gas)
Southwest Gas is conducting main pipe replace on 24th Street west of Avenue 9E. Lane restrictions, speed limit reduction and bike lane closure will take place. This section is part of a larger project on 24th Street expected to wrap by September.
3rd Street, 4th Avenue to Avenue A (Century Link)
CenturyLink has a five-month project to repair telephone cable along 3rd Street, between 4th Avenue and Avenue A. The project which will involve accessing manholes will cause lane closures and in some areas sidewalk closures.
Avenue 3E at 40th Street, 32nd Street
There will be lane closures along Avenue 3E at 40th Street, 32nd Street and at the intersection of Avenue 4E and 41st place through Aug. 6 for a CenturyLink project that requires access to manholes. A reduced speed limit will also be in place.
APS pole work, various locations
APS will install new SCS reclosers on existing poles throughout the area through September 2019. While work will mostly occur on shoulders, some lane narrowing and shifting will take place within work zones. Work zones the city is aware of include the following: • 3rd Street east of Avenue B. • Avenue A at the northeast corner of 16th Street. • 15th Street and Avenue A. • 32nd Street at S.R. 195. • 37th Street at Avenue 5E. • North Frontage Road and Mesa Avenue. • Avenue 8E south of 24th Street. • 12th Avenue south of 7th Street.
• Araby Road south of 24th Street.
• County 11th Street and Westwind.
• Near the corner of Avenue 5E and E. County 10th Street.
• South Frontage Road near Avenue 9E.