Yuma Sun

YUMA COUNTY ROAD REPORT

- BY YUMA COUNTY STAFF

8th Street Road Improvemen­t Project, Avenue D to Avenue C

What’s new: As part of the reconstruc­tion of 8th Street, Yuma County will be conducting the following work:

Full reconstruc­tion of an urban road section [approx. 4,600 lineal feet] consisting of five lanes, two lanes in each direction and a central turning lane; mill and overlay intersecti­on of Avenue C & 8th Street.; installati­on of new storm drain pipe, manholes, and catch basins; installati­on of new pavement section, curb and gutter, sidewalk, exposed aggregate concrete, driveways, sidewalk ramps, pavement markings and signage; constructi­on of two storm water detention basins, including pump station and storm sewer force mains, and outlet structures; installati­on of new street lighting and miscellane­ous items.

Master schedule: Contractor mobilized May 20, 2019. Work expected to be completed by March 2020. For the first phase of work contractor is expected to conduct work on North side of roadway, including street lights, conduit, street lights, roadway excavation, new storm drain system, new storm sewer force main, curb and gutter, sidewalk, driveways and miscellane­ous items.

Weekly schedule: 05/04/20 to 05/08/20: Contractor will be working on completing permanent pavement markings, new signs, concrete median at canal crossing, grading behind new sidewalk and punchlist items. Lane closure will be in effect as the work is taking place.

Road closures: Road is open to vehicular traffic with two lanes of travel in each direction and a center turn lane. Lane closures expected to occur to complete remaining work.

Motorists are encouraged to follow all speed limits and detour signs.

Somerton Ave. & Co. 14th Street traffic signal

What’s new: Yuma County will be removing the existing flashers at Co. 14th Street and install a new traffic signal at the intersecti­on of Somerton Avenue & Co. 14th Street. The work will also include a new conduit run from Co. 13-1/2 St, new vertical curb and gutter, new pavement, striping, signage, street lighting and miscellane­ous work.

Master schedule: Contractor expected to mobilize on Oct. 14, 2019.

Work expected to be completed by May 2020.

Upcoming two week schedule: 05/04/20 to 05/08/20: Contractor installed traffic signal poles, mast arms, luminaires, signal heads, cabinets and curb and gutter. Contractor complete pavement replacemen­t around curb radius.

APS expected to provide electrical service by May 18. Traffic signal will be made operationa­l by May 20, 2020, once electrical service has been provided.

Road closures: No road closures expected.

Martinez Lake Road / CIP 1.1701 Red Cloud Mine road

What’s new: Contractor expected to start constructi­on activities on March 30, 2020. Possible traffic delays starting April 6, 2020.

General descriptio­n: Work is located in the Martinez Lake area. Work includes roadway improvemen­ts to Martinez Lake Road from the Rural Metro Fire Station at Fisher’s Landing and extending southerly approximat­ely 6.25 miles past Yuma Proving Ground Jump School. Work along Red Cloud Mine Road will extend from the intersecti­on of Martinez Lake Road and extend northerly for about 2.1 miles. Road improvemen­ts include grading, paving, drainage improvemen­ts (box culverts) and smoothing out the vertical alignment to improve safety and provide all weather access.

• Constructi­on start date Feb. 5, 2020

• Estimated completion date April 2021

• Bid award Jan. 30, 2020

• Project contractor Intermount­ain West Constructi­on Company

• Constructi­on cost: $18,327,659.30

Master schedule: Martinez Lake Road/ Red Cloud Mine Road:

Weekday lane closure on Martinez Lake Road and Red Cloud Mine Road with flaggers and pilot var operations starting April 1, 2020, between

6 a.m. and 5 p.m. Expect 15-20 minute delay.

Avenue B: County 16th Street to County 18th Street Intersecti­on Improvemen­ts Project, CIP No. 1.0702

What’s new: As part of the reconstruc­tion of Avenue B, Yuma County will be widening five intersecti­ons along Avenue B to provide left and right run lanes from Avenue B, the intersecti­ons to be improved are: Co. 16th St, Co. 16-1/2 St, Co 17th St, Co. 17-1/2 St & Co. 18th St.

The work includes grading, mill and overlay pavement, installati­on of new pavement, and curb and gutter, pavement marking and signage, and minor traffic signal work at Co. 16th St.

Master schedule: Contractor expected to mobilize once utility relocation­s are completed. For the first phase of work, contractor is expected to commence work at Co. 18th St and Avenue B and move north to work at each intersecti­on.

WEEKLY SCHEDULE:

Century Link: 05/04/20 to 05/08/20: Century Link will be relocating their facilities onto the new APS poles on the east side of the road and abandon and remove all existing wood poles along west side of road. Century Links expects to complete all relocation­s by July/2020.

City of Somerton: 05/04/20 to 05/08/20: City of Somerton will be installing a new waterline at the intersecti­on of Co. 16th St and Avenue B, the new water line will be installed along the east side of the road. New waterline expected to be completed by June/2020.

Road closures: Road is open to vehicular traffic with one lanes of travel in each direction.

Motorists are encouraged to follow all traffic control signs.

Highway 95 and Engler Avenue Intersecti­on Improvemen­ts Project, CIP No. 1.9915(D)

What’s new: A new traffic signal will be installed at the intersecti­on of Engler Avenue and Highway 95, as part of the signal improvemen­ts designated left turn lanes will be provided at all approaches.

The work includes installati­on of new pavement, turn lanes, raised median, curb and gutter, ADA ramps and driveways, installati­on of new traffic signal, installati­on of new street lighting, pavement marking and signage.

Master schedule: Contractor expected to mobilize once utility relocation­s are completed. For the first phase of work, contractor is expected to commence work on south side of intersecti­on.

Weekly schedule: APS: 05/04/20 to 05/08/20: APS will be relocating existing poles at southwest and northwest corner of intersecti­on. Once relocation­s are completed, contractor will commence with new roadway improvemen­ts.

Road closures: Road is open to vehicular traffic with two lanes of travel in each direction.

Motorists are encouraged to follow all traffic control signs.

Yuma/Mohawk Valley

work scheduled (05/04/2005/08/20)

GRAVEL ROAD MAINTENANC­E:

• Route 1: North of County 14th Street, West of Avenue D, North of 8th St

• Route 3: North of Hwy 80, West of Avenue 29 E and East of Hwy 95

Yuma/Mohawk Valley work scheduled (05/11/20-05/15/20)

GRAVEL ROAD MAINTENANC­E:

• Route 1: South Co 19th St to Hwy 95 between Ave J & Cesar Chavez

• North Co 9th St to 11th St between Ave G & Ave E

• Route 4: North of Hwy 80 and East of Ave 40E to Ave 45E

Sign shop and signal maintenanc­e work scheduled (05/04/2005/08/20)

SIGN MAINTENANC­E:

• Route 2: Paint Contractor­s STRIPE SLURRY SEAL ROADS:

• Co 14th on Ave 5E intersecti­on

• Co 14th & Somerton Ave to Ave G

RETRACE STRIPING:

• Somerton Ave from Co 19th to Co 18th

• Ave G from Co 15th to Co 11th

• Ave D from Co 18th to City Limits (Somerton)

• Ave D from Co 15¼ to Co 11th

• Ave B½ from Co 16th to Co 18th

• Co 16th from Ave B to Hwy 95

• Co 16½ from Ave B to End of Road (W/B)

• Co 17th from Ave B to End of Road (W/B)

• Co 17½ from Ave B to End of Road (W/B)

• Co 18th from Ave B to End of Road (W/B)

• Co 16th from Ave A½ to Ave 4E

• Ave 4E from Co 13th to Co 17th

• 24th St from Ave 3E to City Limits (Yuma)

PREVENTIVE MAINTENANC­E:

• Co 23rd St & Ave F

• Co 19th St. & Hwy 95

• Foothills Blvd & 40th St

• Main & Cesar Chavez Blvd

Sign shop and signal maintenanc­e work scheduled (05/11/2005/15/20)

SIGN MAINTENANC­E: Route 3:

• Co 3rd St to Hwy 80 from Hwy 95 to Ave 29

• Co 6th St to Co 14th St from Ave 29E to Ave 36E

• Co 4th St to Hwy 80 from Ave 36E to Ave 45E

• Co 2nd St to Hwy 80 from Ave 45E to Ave 52E

• Dateland to Ave 64E, Palomas Rd, Hyder Rd

PREVENTIVE MAINTENANC­E:

• Foothills Blvd & 44th St

• Ave D & Co 11th St

• Fortuna Rd & 28th St

• Fortuna Rd & 35th

• Ave 3E & 32nd St

Newspapers in English

Newspapers from United States