CITY PROJECTS
• Palo Verde Street, Catalina to Arizona
• Main Street, 3rd Street to Giss
• Neighborhoods in the slurry seal and oil seal program
Slurry seal and oil seal
The City of Yuma slurry seal and oil seal applications will affect several major roadways, area neighborhoods, and one major intersection over the next several weeks, but will provide an improved driving surface and nicer look once complete. Work hours will be from 7 a.m. to 5 p.m., with some weekend work to minimize the impact to busier streets.
Slurry seal program
• Nov. 9-13, crews will be working at Palo Verde Estates Units 1, 2.
• Nov. 9-13, main arterials affected at Palo Verde Street from Arizona Avenue to east of Olivia Avenue, Pacific Avenue from 24th Street to 32nd Street, 1st Avenue from 16th Place to 24th Street, Country Club Drive from Catalina Drive to east of Chiquita Drive, 24th Street from Pacific Avenue to east 23rd Lane.
• Nov. 10, work will prompt road closure at 40th Street from Avenue 3-1/4E to Avenue 4E.
Traffic control will be in place indicating detours to alternate routes.
CITY STREET MAINTENANCE
City street maintenance operations for the week of Nov. 9-13 will take place in the following areas:
Street asphalt patching
• Sunridge Drive from 16th Street to 18th Street
• Country Club Drive from Catalina Drive to Chiquita Drive
• Chiquita Drive from Country Club Drive to 32nd Street
• 1335 S. Pacific Avenue
Sidewalk concrete repairs
• 1540 W. 8th St.
• 697 S. 21st Ave.
• 3rd Street and 20th Avenue, south side of the road
• 2240 W. 6th St.
• 1922 W. 6th St.
Street lane striping
Drivers are asked to be cautious of wet paint on the roadway in the following areas:
• Palo Verde Street from Avenue 2-1/2E to Avenue 3E.
• 40th Street from Avenue 3-1/4E to Avenue 4E.
OTHER UTILITY PROJECTS, ENCROACHMENT PERMITS
Palo Verde Street, Catalina Drive to Arizona Avenue
Through mid-March, a contractor will perform road and sidewalk improvements in the areas surrounding Catalina Drive and Palo Verde Street, east of 4th Avenue to 32nd Street, and north along Palo Verde Street.
Work will prompt lane restrictions along Palo Verde Street and Catalina Drive. Additionally, sidewalks will be closed and street parking will be restricted. Traffic control will be in place indicating detours to alternate routes.
Main Street, 3rd Street to Giss Parkway
Through late December, a contractor will install a new raised crosswalk along with modified curb, gutter and sidewalk improvements and spot drainage improvements. Work will require a brief road closure at Main Street between 3rd Street and Giss Parkway at a future date. Traffic control will be in place and detour to alternate routes.
8th Street, 21st Avenue (Southwest Gas)
Sometime through November, Southwest Gas will install gas lines. Traffic control will be in place, shifting lanes and reducing speed limit to 25 mph.
Avenue B, 28th Street (APS)
Now through December, APS will install a new transformer and work on existing poles along the west side of Avenue B, south of 28th Street. Work will require lane restrictions.
4th Avenue, Catalina Drive (Century Link)
Through early November, Century Link will work on communication lines. Work will require lane restrictions at the intersection of Catalina Drive and 4th Avenue.
8th Street, 21st Avenue (APS)
Through early November, APS will remove and replace lines along north side of 8th Street and work on an existing pole near the corner of 8th Street and 21st Avenue, and pull wire along west side of 21st Avenue. Work will require lane restrictions and speed limit of 35 mph. Proceed through the area with caution.
Arizona Avenue, Mesquite Street (Southwest Gas)
Southwest Gas will work on gas lines. This three-month project will require lane shifts along Arizona Avenue. Completion is expected by the end of December.
Arizona Avenue, Country Club Drive (APS)
Now through December, APS will work along the south side of Country Club Drive.
Work will require lane shifts and reduced speed of 25 mph.
Avenue 3E, 38th Street
Through late November, a contractor will pour concrete for new commercial driveway entrances. Work will require lane shifts on Avenue 3E between 38th Street and 38th Place and a reduced speed limit of 25 mph.
16th Street, Yuma Palms (Century Link)
Century Link will work on communication lines along Yuma Palms Parkway at the corner of 16th Street. Work will require lane restrictions. Work is anticipated to be completed by early December.
24th Street, 22nd Drive (APS) Through early December, APS will replace a damaged pole along the north side of 24th Street and 22nd Drive. Work will require lane restrictions and a reduced speed of 25 mph.
Yuma Palms Parkway, Castle Dome Avenue (Century Link)
Century Link will work on communication lines along Castle Dome Avenue prompting lane restrictions and a speed limit of 25 mph. Work is anticipated to be completed by mid-December.
Avenue B, 16th Street (Century Link) Century Link will work on communication lines along Avenue B between 16th Street and 15th Street, requiring lane shifts. Work will take place between now and mid-December.
Catalina Drive, 29th Street (Century Link)
Through mid-December, Century Link will be working in the area of Catalina Drive and 29th Street. Drive with caution in area.
Pacific Avenue, 24th Street (Century Link)
Through mid-November, crews will access manholes for telephone cable repair. Work will require lane restrictions at the intersection of Pacific Avenue and 24th Street.
Various locations, communication line work (Century Link)
Through mid-January, Century Link will work on communication lines in various locations through the city. Work will prompt lane restrictions and reduced speed limit in the following areas:
• Avenue 3E and Palo Verde Street
• Avenue 2-1/2E and Palo Verde Street
• Pacific Avenue and Palo Verde Street
• Arizona Avenue and 24th Street
• Lakin Avenue and Palo Verde Street