Yuma County Road Report

- BY YUMA COUNTY

MARTINEZ LAKE RD / CIP 1.1701 RED CLOUD MINE RD

Work is located in the martinez Lake area. Work includes roadway improvemen­ts to martinez Lake rd from the rural metro Fire Station at Fisher’s Landing and extending southerly approximat­ely 6.25 miles past Yuma Proving Ground Jump School. Work along red cloud mine rd will extend from the intersecti­on of martinez Lake rd and extend northerly for about 2.1 miles. road Improvemen­ts include grading, paving, drainage improvemen­ts (box culverts) and smoothing out the vertical alignment to improve safety and provide all weather access.

• Estimated completion date June 2021

Master Schedule:

Earthwork operations on red cloud mine road completed. Earthwork started on martinez Lake road. Expect 20 to 30 minute delays. There will be a single lane closure with flaggers and a pilot car will be utilized as needed

The box culvert work will be ongoing on martinez Lake road with the current detour in place. Possible one lane closure with flaggers for installati­on of the hdPE waterline for the pond.

road has been restricted to one lane of traffic, Traffic signal is now in place. Please follow all traffic control devices. delays to be expected.

CO. 11TH ST & SOMERTON AVE SAFETY IMPROVEMEN­TS,

CIP NO. 1.1505.

What’s New:

Yuma county will be conducting safety improvemen­ts at co. 11th Street and Somerton avenue intersecti­on; the improvemen­ts include installing enhanced warning signs, stop signs, centerline rumble strips, transverse rumble strips, street lighting on existing aPS poles, speed radar signs and miscellane­ous items.

Master Schedule: contractor has been issued the notice to proceed and is in the process to acquire all materials.

WEEKLY SCHEDULE: 03/22/2021 to 03/26/2021: contractor to complete installati­on of new solar signal equipment, including enhanced stop signs, speed radar signs by 03/16/21. due to chip seal road maintenanc­e, remainder of road improvemen­ts scheduled to be completed by 04/16/21.

Road Closures: no road closures are scheduled at this time.

COUNTY 15TH ST – AVENUE A INTERSECTI­ON IMPROVEMEN­T PROJECT CIP

NO. 1.9915E

What’s New: a new traffic signal will be installed at the intersecti­on of co. 15th Street & avenue a, as part of the signal improvemen­ts designated left turn lanes will be provided at all approaches.

The work includes Install Traffic Signals, Street Lights and Traffic Signal Equipment, widen roadway for right and Left Turn Lanes and ac Overlay, remove, replace undergroun­d siphon with 36” diameter c-905 pipe, minor irrigation canal modificati­ons to accommodat­e new longer undergroun­d siphon, widen roadway for right and Left Turn Lanes and ac Overlay, Sawcut and remove pavement, minor earthwork and grading.

Master Schedule: contractor mobilized on monday november 23,2020. For the first phase of work contractor commenced work on south side of intersecti­on. contractor will me removing irrigation siphon, removing existing pavement and grade roadway for new road improvemen­ts. during second phase of work, contractor will be installing new traffic signal poles, widening intersecti­on and completing intersecti­on reconstruc­tion. WEEKLY SCHEDULE:

DPE Constructi­on: 03/22/2021 to 03/26/2021: Signal expected to be activated by 03/25/21

Road Closures:

03/22/2021 to 03/26/2021: no road closures expected during this period. Intersecti­on to remain a 4- way stop until signal operationa­l.

YUMA & MOHAWK SPRING 2021 CHIP SEAL PROGRAM.

CIP NO. 1.1201

What’s New:

Yuma county to conduct road maintenanc­e on multiple roads in the Yuma and mohawk area. approximat­ely 31 miles of roadway will receive a chip seal, fog seal & new striping, the roads include the following locations

Master Schedule: contractor expected to mobilize by march 22, 2021.Work is expected to be completed by may 31,2021.

WEEKLY SCHEDULE: 03/22/2021 to 03/26/2021: contractor to commencer work on mohawk area starting 3/24/21.

Road Closures:

03/22/2021 to 03/26/2021: Pilot truck and flaggers will be in place during chip seal operation, delays up to 10 minutes are expected. drivers are encouraged to use alternate routes.

SOUTH SOMERTON DRAINAGE IMPROVEMEN­TS. CIP NO. 3.0504B

What’s New:

Yuma county Flood control district will be conducting drainage improvemen­ts at several locations in the city of Somerton. Phase 1 is the constructi­on of the Bingham avenue Storm drain and the rollow Estates Storm drain System. Phase 2 is the constructi­on of the union avenue Storm drain System. The work includes: a) Installati­on of 18” thru 30” storm drain pipe, concrete inlet and outlet headwalls, and minor retention basin grading. b) Storm water pump station, force main, and force main connection­s. c)Sidewalks, curb and gutter, pedestrian curb ramp replacemen­ts, and miscellane­ous concrete work. d) Pavement replacemen­t. e)miscellane­ous water and sewer relocation­s. Master Schedule:

Gutierrez Canales Engineerin­g, PC:

03/22/2021 to 03/26/2021: contractor expected to mobilize once utilities complete relocation­s along Bingham avenue. no work scheduled for march 2021. Utilities:

03/15/2021 to 03/31/2021: aPS expected to continue with relocation­s. century Link, Spectrum & SWG to conduct work concurrent­ly with aPS.

WEEKLY SCHEDULE: 03/22/2021 to 03/26/202121: : utilities will be adjusting facilities to avoid new storm drain system. Lane closures and potential road closures to take place as needed to complete work

Road Closures:

03/22/2021 to 03/26/2021: : road closures may be permitted to allow utilities to conduct relocation­s. detour will be in place, drivers are encourage to follow all traffic control signs and use alternate routes.

YUMA/MOHAWK VALLEY WORK SCHEDULED 3/22/21 to 3/26/21

GRAVEL ROAD MAINTENANC­E:

Route 1:

• ave G to ave B

• co 15th St to co 13th St

• hwy 95 to ave E

• co 17th St to co 14th St Route 2:

• ave B to ave 2E

• co 18th St to co 14th St Route 3:

• ave 27E to ave 32E

• co 12th St co 6½ St

Route 4:

• Tacna Town Subdivisio­n

• ave 40 to ave 43E

• hwy 80 to co 5th St SLURRY SEAL: 3/18/21 – 3/25/21

• Seasons Subdivisio­n

• Fortuna heights Subdivisio­n WORK ZONE:

3/23/21 – Bridge clean-up & repair on ave 20E & Wellton mohawk canal

SIGN SHOP & SIGNAL MAINTENANC­E WORK SCHEDULED 3/22/21 to 3/26/21

SIGN MAINTENANC­E:

Route 1:

• hwy 95 at San Luis city Limits to co 19th St

• co 19th St to ave G

• ave G to co 20th St

• co 21st St from hwy 95 to ave I

Including all other road segments within these areas

Route 2:

• ave 12E from S Frontage rd to 40th St

• 40th St from ave 12E to Foothills Blvd

• Foothills Blvd from 40th St to S Frontage rd

• S Frontage rd from ave 12E to Foothills Blvd

Including all other road segments within these areas

Route 3:

• ave 24E from co 9th St to hwy 80

• co 10th St from ave 24E to ave 22E

• co 9th St from ave 20E to ave 24E

• hwy 80 from ave 20E to ave 24E

• co 8th St from ave 19E to ave 22E

• co 7th St to east of ave 20E Including all other road segments within these areas

PREVENTIVE MAINTENANC­E:

• co 22nd St & ave F

• main St & cesar chavez

• main St & urtuzua dr

• archibald & urtuzua dr

• W Brooks & cesar chavez

• 8th ave & main St

• co 21st St & main St

• main St & Piceno dr