Yuma Sun

City of Yuma Road Report

-

BY THE CITY OF YUMA

a weekly list of City projects or encroachme­nt permits issued by the City of Yuma affecting busy streets.

CITY PROJECTS

North Frontage Road, Avenue 9E to Avenue 10E Yuma Commerce Center sewer line extension – 7E closure

Beginning nov. 22, avenue 7e will be closed to all traffic between 30th Street and 32nd Street for sewer line and manhole installati­on. business access detour is from the west end of 30th Street via araby road or from north Frontage road/avenue 8e from the east end of 30th Street. This phase of work will last through at least mid-december.

A contractor working for the City is installing a sewer line extension, new sewer manholes and new sewer line services in the Yuma Commerce Center, affecting the following roadways:

• avenue 7e from 32nd Street, north to 29th Street, including 31st Place and 30th Street.

• 31st Place from avenue 7e east to the Plaza del este area.

• 30th Street from avenue 7e east to Commerce Center drive.

• 29th Street from avenue 7e east to Commerce Center drive.

• Commerce Center drive from 29th Street south to 30th Street.

• motorists are advised that there will be delays, detours, lane shifts and closures on these roadways.

City Street Maintenanc­e

City Street maintenanc­e operations for the week of nov. 22-26 will take place in the following areas. Crack Sealant

• 16th Street from arizona avenue to Yuma Palms Parkway.

Street Asphalt Patching

• mission Street from araby road to avenue 7e.

• Telegraph Street from araby road to avenue 7e.

• 2600 block of barbara avenue. Sidewalk Concrete Repairs

• 600 block of 2nd Street.

• 700 block of 2nd Street.

• 200 block of 6th avenue. Other utility projects and

encroachme­nt permits

Avenue B, 8th Street (private contractor)

Through late december, crews will perform undergroun­d utility work along avenue b and 8th Street. Work will prompt lane shifts and a reduced speed limit of 25 mph.

Araby Road, 24th Street (Southwest Gas)

Southwest Gas will replace a gas line along 24th Street and araby road. Work in the area will require lane restrictio­ns through late december.

Avenue 3E, Palo Verde Street (Century Link)

Through late december, Century Link will perform communicat­ion line work that will prompt lane restrictio­ns along avenue 3e and Palo verde Street.

4th Avenue at 5th Street (Wanrack)

a contractor will install new fiber optic lines, requiring a right lane closure of southbound 4th avenue approachin­g 5th Street. This 5-day project should conclude by the end of november.

16th Street, Avenue B (Century Link)

Through late november, Century Link will perform communicat­ion line work that will prompt lane restrictio­ns along avenue b and 16th Street and a reduced speed limit of 35 mph.

Avenue B at Claxton Street (Southwest Gas)

Southwest Gas will perform gas line work along avenue b and Claxton Street. Work in the area will require lane shifts through late december and a reduced speed limit of 25 mph.

Avenue 3E, 42nd Street (Century Link)

Century Link will access manholes for line maintenanc­e work that will prompt lane shifts along avenue 4e and 42nd Street and a reduced speed limit of 25 mph. Work should be completed by late december.

8th Street, Avenue C to Avenue D (Century Link)

Century Link will access manholes for line maintenanc­e work that will prompt lane shifts along 8th Street between avenue C to avenue d and a reduced speed limit of 25 mph. Work should be completed by late december.

16th Street, 13th Avenue to 14th Avenue (Century Link)

beginning oct. 20, Century Link will access manholes for line maintenanc­e work that will prompt lane shifts along 16th Street between 13th avenue to 14th avenue and a reduced speed limit of 25 mph. Work should be completed by late december.

24th Street, between James Avenue and James Drive (Century Link)

Century Link will access manholes for line maintenanc­e work that will prompt lane restrictio­ns along 24th Street between James avenue and James drive. Work should be completed by late december.

Avenue B, 8th Street (contractor)

Through late december, crews will be performing undergroun­d utilities work along avenue b and 8th Street. Work will prompt sidewalk closure and lane shifts.

Avenue 5E, 32nd Street to County 13th Street (Century Link)

Century Link will install conduit and fiber along the northbound lane of avenue 5e between 32nd Street and County 13th Street between nov. 30 and Jan. 31, 2022. Work will tie in along cross streets. Lane closures may take place at times.

24th Street, Avenue A (contractor)

beginning nov. 15, contractor will pour concrete, a landscape wall, and other amenities. Work will prompt lane restrictio­ns along 24th Street and avenue a, a sidewalk closure and a reduced speed limit of 25 mph. Work is anticipate­d to be completed by early may 2022.

16th Street, 13th Avenue to 14th Avenue (Century Link)

Century Link will access manholes for line maintenanc­e work that will prompt lane shifts along 16th Street between 13th avenue to 14th avenue and a reduced speed limit of 25 mph. Work should be completed by late december.

24th Street, Arizona Avenue (Century Link)

Through mid-January, Century Link will remove and restore sidewalk concrete along 24th Street and arizona avenue.