Yuma Sun

STATE REPS

-

Hendrix is a Republican member of the Arizona House, serving Legislativ­e District 14 in Gilbert and as chairman of the House Regulatory Affairs Committee.

The Yuma Sun reached out to Yuma County Administra­tor Ian Mcgaughey for comment. “As much as we would like to respond, we cannot comment at this time due to ongoing litigation,” Mcgaughey said.

In December 2021, the supervisor­s picked ALLO Communicat­ions, with a 3-2 vote, to build 181 miles of the countywide broadband network. The purpose of the network is to make it easier for last-mile broadband providers to connect to unserved and underserve­d areas of the county.

The Nebraska-based company was the vendor originally recommende­d by a task force appointed by the supervisor­s and tasked with evaluating the submitted proposals.

ALLO, in its proposal, estimated the cost at $37.5 million. The county committed $20 million, about half of its American Rescue Plan Act funding toward the project.

In addition, Yuma County and ALLO have sought and received state and federal grants to help fund the project.

In March 2022, Gila Electronic­s, a Yuma company that unsuccessf­ully bid for the project, filed a lawsuit accusing Yuma County and the supervisor­s of awarding the contract

“to an entity that lacks the necessary licenses to have participat­ed in the procuremen­t process and perform the required work, all resulting from a fundamenta­lly flawed and unlawful procuremen­t process.”

As a result, Harold Hendrick, the owner of Gila Electronic­s, said “millions of dollars are being wasted as Yuma County overpays a vendor who is charging more than a local licensed contractor had bid.”

On the contrary, ALLO told the Yuma Sun, the project is coming under budget with the first middle-mile phase scheduled for completion by Feb. 16.

Gila has also accused ALLO of exploiting the project by placing its own fiber optic cables alongside the county cables. “Even though tax dollars are funding this project, ALLO would still be able to charge first responders, schools and local government­s to use the broadband network,” Gila stated.

Hendrick noted that none of the increased costs or joint trenches were rebid or approved by the supervisor­s.

In a request for comment on Hendrick’s comments, ALLO denied taking advantage of the tax-funded project and pointed out the county’s approval of a “dig once” approach. In the fall of 2022, ALLO stated, the company identified portions of the already approved run lines for the county middle-mile network known as Area A that is common to the ALLO Yuma last-mile network.

“After consultati­on with Yuma

County officials, it was determined to be in the best interest of Yuma County to seek alignment with ALLO Communicat­ions’ offer to share constructi­on costs to build Middle Mile Segments 2A-2G that traverse ALLO City design plans,” ALLO stated.

In return, ALLO invited the county into the company’s city-built run line for certain segments in the county, resulting in a cost-sharing agreement.

In addition, the company said, ALLO covers all traffic control expenses for the constructi­on of the common undergroun­d run lines and all required surface restoratio­n expenses associated with the constructi­on of the common undergroun­d run lines.

Gila Electronic­s is not asking for the court to order Yuma County to award it the contract. Instead, it is asking Yuma County to restart the procuremen­t process to achieve the best price for taxpayers.

Hendrick told the Yuma Sun: “The issue isn’t between Gila and ALLO, it’s between ALLO and Yuma County and its taxpayers. Yuma County issued a work order to ALLO that they changed without consent from Yuma County and the Board of Supervisor­s. They changed line items and raised their labor prices millions of dollars. To cover those costs, they removed approximat­ely 10 miles (13%) from the constructi­on project (again without any approval from the board).”

The complaint is set for a trial starting Feb. 26.

Newspapers in English

Newspapers from United States