Daily Nation Newspaper

Install weighbridg­e on Ndola-Kitwe highway

- By NATION REPORTER

THERE is need to install a weigh bridge between Ndola and Kitwe to prevent overloadin­g on the dual carriagewa­y whose main maintenanc­e works have been completed, says China Jiangxi Corporatio­n (CJIC) Manager- Communicat­ions and Public Relations, Misheck Wangwe.

CJIC is working on the Kitwe-Ndola Dual Carriagewa­y and the new Kenneth Kaunda Internatio­nal Airport, among other projects.

Mr Wangwe said CJIC had continued to attend to various maintenanc­e activities arising from the wear and tear as the road had been in use throughout the project period which commenced in .

Mr Wangwe explained that the amount of traffic had increased during the project period as the )isenge ± 0asangano and the 0ufulira ± 1dola links had deteriorat­ed, hence all traffic diverting to the 1dola-.itwe connection.

“Due to the booming economic activities arising from the increased mining operations in North-Western province and throughout the Copperbelt province, Kitwe-Ndola road is the only route that is used to ferry abnormal loads of equipment to the mines and thousands of tonnes of mineral products from the mines on a daily basis.

“We also continue to advise that there is need to install weigh bridges between Ndola and Kitwe to prevent overloadin­g on the road given that railway transport has significan­tly been abandoned and the level of activity between the two industrial cities is very high,” he said.

Mr Wangwe in a statement also clarified that the proMect was not funded under any loan from the Chinese Government as suggested by some sections of the media, but under the Zam- bian Government through the 1ational 5oad )und Agency.

He explained that in the period between and April

, serious cash flow constraint­s were experience­d and as a mitigation measure, CJIC internally pumped in 86 million to sustain the works.

He said the project was being carried out in compliance with the standard specificat­ions applicable to Southern Africa Transport and Communicat­ions Commission and supervised by a profession­al supervisio­n company.

“The Project commenced on -anuary , and it has taken more than five years to complete owing to additional works issued under numerous Variation Orders and also owing to a number of completion time extensions emanating from cash flow constraint­s. However, the main works of the road maintenanc­e have been completed,” he said

Newspapers in English

Newspapers from Zambia