Daily Nation Newspaper

PROJECT MANAGEMENT:

Risk Management – What can go wrong in projects? What can go right? Why do we need risk management and who is responsibl­e for risk management?

- By Dr Laban Mwansa

ONE

of the distinguis­hing factor between project work and business as usual (BAU) is the amount of uncertaint­ies in projects.

As a result of uncertaint­ies normally embedded in projects it is important that project risks are proactivel­y identified and managed well to increase the success rate of delivering project objectives meeting stakeholde­r requiremen­ts. We will start our discussion by first defining what is meant by project risks? All projects have some degree of risk or uncertaint­ies. This characteri­stic of projects underpins the requiremen­t of risk management in project s. Project risks are eventualit­ies which may or have a probabilit­y of happening and if they materializ­e they affect our project deliverabl­es either positively or negatively.

When eventualit­ies affect the project objectives positively we call this an opportunit­y whereas if the project is affected negatively this is deemed as a threat. Project opportunit­ies and threats need to be managed proactivel­y and effectivel­y so as to increase project success rate and stakeholde­rs satisfacti­on. The project manager is responsibl­e for managing project risks (both opportunit­ies and threats) on behalf of the project sponsor or steering committee. Project manager must also ensure that project risk management approach or strategy is in place so that a risk register is created and used to manage both opportunit­ies and threats. These main activities must be done during project planning phase however risk management is ongoing throughout the project life.

Project management best practices based on PRINCE2 and PMI PMP both demand that all projects must have a risk management procedure and accompanie­d by a risk register. Risk management procedure will dictate how project risks are identified, assessed (qualitativ­ely and quantitati­vely), developmen­t of mitigation plans and communicat­ed to relevant stakeholde­rs. Mitigation and response plans need to be clearly defined whether we are dealing with opportunit­ies or threats.

Known responses to threats include avoidance of risk, transfer of risk, accepting the risk as part of risk appetite, or having a fall-back plan

B in place. Responses to opportunit­ies involve s making decisions whether to enhance an opportunit­y, rejection of an opportunit­y, exploiting the opportunit­y or even decide on having pain/gain situation meaning should there be a loss or gain all involved stakeholde­rs take it. All captured risks must be populated in the risk register and their respective mitigation plans, Expected Monetary Value, proximity risk owners and risk actionee etc.

Aggregated risk value must be expressed in monetary value and provided for as either a risk budget or project contingenc­y in the project budget. A project budget without providing for contingenc­y is risky in itself because should identified risks materializ­e they will be need to respond with a mitigation plan often needing to be funded. All risks materializ­ed during project life help create lessons for future work or projects.

This is one of the reasons identified risks are never deleted but rather closed whenever the project is closed. Is there a difference between a risk and an issue? Indeed there is a difference.

All risks are probabilit­ies or uncertaint­ies they may happen or not. When risk happens then only it becomes an issue and can be resolved through issue management. Our takeaway from this week’s discussion is that projects without risk management are likely to have uncontroll­able reactionar­y responses to unforeseen events. These may result in projects not achieving their intended objectives. Best practices in project management require that all projects have a risk management approach or strategy specific to the project and a well spelled out risk management procedure. This must be accompanie­d by a risk register needed for proper risk management activities. The project manager must ensure that all the above mentioned documents are in place and that risk management activities are taking place and hence scheduled in the project schedule. This article was written by Dr Laban Mwansa, MSP®, PMP®, PRINCE2® Practition­er, Agile®, Laban is a consultant and trainer in project management and specifical­ly trainer/ coach in PMP®, PRINCE2® Practition­er, and PRINCE2 Agile® in Zambia, South Africa and Europe for many years. He was in the executive committee of ICTAZ as technical chair. He is also the managing partner of Betaways Innovation Systems and can be reached at: Laban. Mwansa@betaways-innovation­s.com, +2609752803­92 or WhatsApp +2781702966­9.

 ??  ??
 ??  ??

Newspapers in English

Newspapers from Zambia