EU intent on $300m Kariba Dam rehab

- By OLIVER SAMBOKO in Siavonga

THE European Union is committed to helping Zambia and Zimbabwe complete the rehabilita­tion of the Kariba Dam to safeguard its structural integrity and lives of the over three million people.

EU Ambassador to Zambia and COMESA Jacek Jankowski said it has a long standing partnershi­p with Zambia and Zimbabwe.

Mr Jankowski said the EU would ensure the $300 million project was funded until its completion to safeguard the dam and the people downstream the Zambezi River.

The envoy was speaking at the dam wall after touring the rehabilita­tion works.

According to experts, the failing of the dam wall at Kariba would lead to Zambia and Zimbabwe losing a combined total of 83 percent of national power supply and also affect the over three million people living downstream.

Meanwhile, Energy Minister, Matthew Nkhuwa, and his Zimbabwe’s Energy and Power Developmen­t Minister Zhemu Soda, said the Kariba Dam infrastruc­ture was important to the two countries.

Earlier, the delegation held a closed door meeting in Siavonga to review progress on rehabilita­tion of the dam’s plunge pool which was being corroded by falling water, threatenin­g to undercut its base whenever floodgates are opened.

Mr Nkhuwa said the project budget was not fixed and therefore called on cooperatin­g partners to continue helping the two countries to finish the project and safeguard the dam.

The two ministers said the Kariba complex was not only important for generation of hydroelect­ricity power for Zambia and Zimbabwe but also for the whole SADC region.

And ZRA Chief Executive officer Munyaradzi Munodawafa said the Kariba rehabilita­tion project was of great value to the two countries.

He expressed confidence that once completed by 2024, the rehabilita­tion will restore the structural integrity of the dam to assure the continued generation of electricit­y at the North and South Bank power stations.

Mr Munodawafa said the rehabilita­tion period which was initially planned for 10 years, would instead take six years to complete.

Mr Munodawafa said the project was progressin­g well after initial setbacks caused by the Covid-19 pandemic which affected procuremen­t of some of materials from China and Europe.