Chronicle (Zimbabwe)

CBZ $12m housing project 85pc complete

- Leonard Ncube in Victoria Falls

SERVICING of roads and sewer infrastruc­ture under the CBZ Holdings $12 million housing project in Victoria Falls is 85 percent complete and beneficiar­ies are likely to be allocated fully serviced stands next month.

Town Clerk Mr Ronnie Dube said this after a joint tour of the site with the bank representa­tives and engineers last week. Mr Dube said the municipali­ty was happy with the progress.

“We had a site visit and we noticed roads have been made while the water system has been connected and what’s left is connecting sewer to the existing system.

“All in all the project is 85 percent complete and we are happy as council with progress made so far taking cognisance of the fact that some works were disturbed by the rains.

“What we are getting is that they will be done by April and fully serviced stands will then be allocated,” said Mr Dube.

He said the site visit was only for stakeholde­rs to appreciate progress in the project, which will see close to 1 174 beneficiar­ies getting housing stands as part of council efforts to complement Government’s efforts to provide houses to low income earners.

Of these about 1 008 will be high density and the remaining 166 stands being medium density housing in line with the financial institutio­n’s strategy to deliver low cost housing.

Councillor­s had earlier in the week, during a full council meeting, demanded a progress report showing beneficiar­ies of the scheme but Mr Dube said selection was being done by the bank, which was yet to furnish the local authority with such details.

He said being on the council waiting list was not a privilege but a process of being in a queue for allocation of a housing stand.

CBZ Holdings was represente­d by head group projects and estates manager Engineer O Sawadya.

Briefing the touring delegation, project engineers said the past two months had been a challenge due to excessive rainfall while they needed sunlight conditions to tar roads.

The engineers said this contribute­d to missing of the February deadline.

The housing project covers the Buffer Zone between Mkhosana and Chinotimba suburbs as well as along Victoria FallsKazun­gula Road and south of Mkhosana. The road network in the project covered 15km combined.

CBZ, which was recently engaged by Government to build student and staff accommodat­ion at tertiary institutio­ns, has channelled $70 million towards various low, medium and high density housing schemes as a private developer or in conjunctio­n with municipali­ties across Zimbabwe.

CBZ developed more than 1 000 stands in Gweru and also serviced residentia­l stands in the Grange in Harare, Chikanga in Mutare, Mbizo in Kwekwe, while similar plans are underway in Bulawayo and Marondera as the bank seeks to contribute to housing delivery as espoused in the country’s economic blueprint, Zim-Asset.

The national housing backlog is more than 1,2 million. The housing waiting list in Victoria Falls currently stands at 15 000. — @ncubeleon

Newspapers in English

Newspapers from Zimbabwe