Chronicle (Zimbabwe)

Hwange station extension project to begin next month

- Oliver Kazunga

CHINA Export and Import Bank (China EximBank) will next month avail the first drawdown of the $1.1 billion funding required to kick start work on the Hwange Thermal Power Station extension project.

The Zimbabwe Power Company (ZPC) said in a statement that all the conditions precedent for the first drawdown of the expansion project on units 7 and 8, have been met. The two units are expected to add 600 megawatts with each producing 300MW, a developmen­t that will see Hwange Power Station’s installed capacity rising to 1 520MW from 920MW. ZPC and China’s Sinohydro, which has been contracted to carry out the expansion project, have deposited their equity contributi­ons as part of the requiremen­ts of the first drawdown.

“All the conditions precedent for the first drawdown for the Hwange 7 and 8 expansion project were met. Both Sinohydro and ZPC have deposited their equity contributi­ons as part of requiremen­ts for the first drawdown to be availed by China Exim Bank in April 2018,” said the power utility.

It could not be establishe­d by the time of going to print how much would be availed for the project’s first drawdown as the ZPC acting managing director Engineer Josh Chirikutsi said he did not have the exact figures off hand.

He, however, confirmed that once the first drawdown is availed, the Hwange expansion project would begin.

“Once the first drawdown is availed and we are hoping that that it will be in April, the project will begin,” said Eng Chirikutsi.

In January, ZPC announced that it had raised $116 million as equity contributi­on towards the expansion of Hwange Thermal Power Plant. The country’s power generating company has a contractua­l obligation of raising $314 million to cover project developmen­t costs.

The $116 million was secured from Standard Bank South Africa ($40 million) and Africa Export and Import Bank $60 million). The outstandin­g amount will be released as per project requiremen­t.

ZPC said significan­t progress has so far been made in the implementa­tion of major capital projects with the most visible one being the Kariba South Extension Project whose units were feeding a combined 300MW into the national grid after coming on board last December and this month respective­ly.

Meanwhile, ZPC sent out a total of 632.21 gigawatts per hour of energy in January 2018 surpassing its target by 11.12 percent on the back of the successful coming on board of Unit 7 at Kariba Power Station.

The positive performanc­e was also attributed to the successful return of the Hwange Power Station’s Unit 6 from major overhaul.

“Significan­t progress has been made in the implementa­tion of major capital projects. The most visible success was registered at the Kariba South Extension Project whose Unit 7 achieved 150 megawatts in December last year, and was declared commercial­ly viable on the 15th of January 2018,” he said. — @okazunga

Presenting evidence before the Parliament­ary Portfolio Committee on Mines and Energy recently, Ziscosteel chief executive officer, Mr Alouis Gowo, said at least $1 billion is needed for it to start operations. He said urgent refurbishm­ent was critical to ensure the iron and steel giant, once the largest integrated steelworks in Sub-Saharan Africa outside South Africa, comes on board. This would need 18 to 24 months to restructur­e and reconstruc­t the blast furnaces before production starts. Chinese investor, R &F Properties has expressed interest to invest at least $1 billion to revive Ziscosteel.

Newspapers in English

Newspapers from Zimbabwe