Chronicle (Zimbabwe)

More investment into electricit­y generation needed

-

ZIMBABWE has added 300 megawatts of electricit­y to the national grid after the $533 million Kariba South Power Station Extension Project was commission­ed on Wednesday. The inaugurati­on of Units 7 and 8 at the hydro plant by President Emmerson Mnangagwa is a milestone which adds a huge amount of energy to a system that has failed to meet demand for 11 years. Although the new generation will not be enough help aggregate power output to meet demand, it is indeed an important addition.

Our country, like many in Sadc started experienci­ng electricit­y shortage in 2007 as consumptio­n overtook output. Government­s in the region failed to marshal investment into new generation at a time when industrial developmen­t, hence demand, was rising. The incongruen­ce caused the current shortages and pushed authoritie­s to attract more resources into energy production.

The Government engaged China for support. They agreed on adding two units of 150MW each at Kariba South and 600MW to Hwange Thermal Power Station.

On November 10, 2014, Sinohydro, a Chinese State-owned hydro-power engineerin­g and constructi­on company began work on the Kariba South Extension Project. In 41 months the company completed the project leading to its commission­ing on Wednesday.

“I am extremely and pleasantly surprised and grateful that from a mere concept in a room in Harare, Government decided to have this Kariba South Extension. Today we are seeing the actualisat­ion of that concept,” President Mnangagwa said.

“It is a great wonder. It tells you what we can achieve as a Government in collaborat­ion with our domestic institutio­ns as well as the importatio­n and collaborat­ion with our partners to access technology from friends of the country.”

Following the expansion of Kariba, the hydro facility now has a nameplate capacity of 1 050MW as it was already capable of producing 750MW. On a national scale, Zimbabwe Power Company (ZPC) is dispatchin­g 1 200MW which is, however, 600MW lower than average daily demand.

This means that the utility should intensify measures to boost power output by expediting the refurbishm­ent of Hwange Thermal Power Station. At the same time it needs to ensure that the planned constructi­on of solar farms in the country and harnessing of other energy options are speeded up.

It is good that financial closure for the Hwange project is due next month. Sinohydro won the $1,5 billion contract to add 600MW to 920MW that the coal-fired plant is capable of producing. The project is envisaged to take 42 months to complete.

ZPC says all conditions precedent for the first drawdown of $199 million for the Hwange 7 and 8 Expansion Project were met. Sinohydro and ZPC have deposited their equity contributi­ons as part of requiremen­ts for the first drawdown to be availed by China Exim Bank. Considerin­g what has been done so far, we don’t see any obstacles arising to delay the consummati­on of the project.

It is with regret that we note the controvers­y that has dogged the Government’s efforts to harness the solar potential the country has. There has been no progress at Insukamini, Gwanda and Munyati where the Government wants three solar farms of 100MW each to be built. The Gwanda tender, for instance, has been marred by allegation­s of corruption involving the winning tenderer, Intratrek and the company’s failure to do any work despite the fact that it was paid money a few months ago.

All involved should work harder for the controvers­ies and delays in the country’s pursuit of its solar ambitions are overcome as soon as possible.

Refurbishm­ent work at smaller coal-fired power stations at Harare, Munyati and Bulawayo hasn’t started for reasons we aren’t aware of yet it should have begun months ago.

The Zambezi River gives Zimbabwe and Zambia much electricit­y at Kariba, and Mozambique further downstream at Cahora Bassa but the three neighbours are only utilising a fraction of the river’s potential. The $4 billion Batoka Gorge Hydro-Power plant to be shared by Zimbabwe and Zambia seeks to exploit the river more. It remains on the drawing board years on. The challenge is likely the fact that no willing investor has come along given the large capital outlay involved.

We were encouraged when President Mnangagwa highlighte­d the need for the country to develop coalbed methane for power generation. Like solar, this is one possible energy option that is crying out for investment. He mentioned that the LupaneHwan­ge area has an estimated 765 billion cubic metres of methane which is a large resource.

This is only a preliminar­y estimate which, we must add, must be confirmed by more investment into exploratio­n not only in the Lupane-Hwange sector, but also other likely deposits in the southeast lowveld and portions of Zambezi Valley in Mashonalan­d West and Mashonalan­d Central provinces.

But an important fact to highlight is that investment into new generation must go hand in hand with correspond­ing investment into power transmissi­on and distributi­on infrastruc­ture. It does not make sense to expand Kariba South and Hwange Thermal, build the Batoka hydro and gasfired capacity in Lupane when the plants would end up being neglected.

Constructi­on of lines to transmit and distribute the expanded output to users is just as critical as building of new generating capacity. The users we are referring to are new ones who remain unconnecte­d to the national grid. Also, as the economy recovers and grows, demand for electricit­y will increase hence the need for more resources to be invested into energy production, transmissi­on and distributi­on.

 ??  ??
 ??  ??
 ??  ??

Newspapers in English

Newspapers from Zimbabwe