Chronicle (Zimbabwe)

Second quarter power generation below target: ZPC

- Oliver Kazunga

THE Zimbabwe Power Company (ZPC) says electricit­y generated in the second quarter of the year was 7,56 percent below target on the back of a host of challenges.

ZPC generates electricit­y from the Hwange Thermal Power Station, the Kariba Hydro Power Station and three small coal-fired power stations, Munyati in Kwekwe, Harare and Bulawayo.

In a performanc­e update, the power utility said the second quarter of the year was characteri­sed by a cocktail of challenges including dropping lake levels at Kariba.

“As a result, ZPC had to curtail generation at Kariba South Power Station to try and maintain the recommende­d generation levels of 358 megawatts at Kariba,” said the power utility in the update.

At a recent energy journalism workshop in Harare, ZPC business performanc­e manager Engineer Bernard Chizengeya said the country’s giant hydro power plant at Lake Kariba was set for decommissi­oning next month in the wake of fast dwindling water levels. At that time, the Kariba water level was at 478 metres and power production was to cease if the water level got to 475 metres.

ZPC said Unit 6 at Hwange, the biggest unit, was unavailabl­e throughout the quarter due to a rotor earth fault, and generation was also constraine­d due to numerous forced outages and diesel stock outs which delayed units’ return to service.

“Cash flows remain a challenge for us as current allocation­s are inadequate to meet critical obligation­s.

“Coal suppliers faced challenges in meeting their delivery targets for the period, resulting in depleted stock levels at the thermal stations. Resultantl­y, ZPC missed the monthly generation targets for the first time in 2019.

“From a target of 2,440,86 Gigawatt per hour, we sent out 2,256, 28GWh of energy thereby missing the set target for the quarter by 7,56 percent,” said the power company.

The second quarter of the year was highlighte­d by the landmark signing ceremony of the Deka project contract with Technofab of India on the 13th of May 2019.

Power projects in progress include the Hwange Expansion which was at 18 percent to completion.

“Transmissi­on and distributi­on works for the project are progressin­g well with about 214,49 kilometres having been cleared as at July 22, 2019,” said ZPC.

Going forward, ZPC believes that with secure funding for the Bulawayo Repowering and Deka Pipeline Projects, they will be a step ahead in alleviatin­g the power shortages Zimbabwe is experienci­ng.

But as for now the immediate solution is importing from regional utilities such Eskom of South Africa and HCB of Mozambique. — @okazunga.

Newspapers in English

Newspapers from Zimbabwe