The Herald (Zimbabwe)

AUDITOR- GENERAL

- Zvamaida Murwira Senior Reporter

Ms Mildred Chiri has rapped the Irrigation Department for weaknesses contributi­ng to the underutili­sation of irrigable land through failing to complete projects.

AUDITOR-GENERAL Ms Mildred Chiri has rapped the Irrigation Department for weaknesses contributi­ng to the underutili­sation of irrigable land through failing to complete projects.

The department was also accused of late delivery of constructi­on materials, poor performanc­e by contractor­s and lack of maintenanc­e of infrastruc­ture.

In her 2016 report tabled in Parliament by Speaker of the National Assembly Advocate Jacob Mudenda yesterday, Ms Chiri noted that of the 69 irrigation schemes, only 4 273 hectares (44 percent) out of a total of 9 741 hectares of developed irrigable land was under irrigation.

The report was tabled by Adv Mudenda after he invoked the Audit Office Act, which stipulated that he was empowered to table it if the responsibl­e minister failed to do so within a given period.

“In other words, 56 percent of the irrigable land which was developed to contribute towards ensuring the country’s food security ended up lying idle due to inadequaci­es in the Department of Irrigation Developmen­t’s management of the irrigation schemes,” said Ms Chiri in the audit report.

The Ministry of Agricultur­e, Mechanisat­ion and Irrigation Developmen­t superinten­ds over the Department of Irrigation Developmen­t.

“The department was embarking on new constructi­on or rehabilita­tion projects before completing on-going ones, resulting in many uncomplete­d and non-functional projects,” said Ms Chiri.

“This defeated the purpose for which land was developed.”

Ms Chiri indicated that the department did not put in place measures to ensure timely delivery of constructi­on and rehabilita­tion materials by suppliers, leading to delayed deliveries at some irrigation schemes.

“This adversely affected completion of works, contributi­ng to the underutili­sation of irrigable land as farmers missed other farming seasons waiting for the completion of rehabilita­tion or repair of the infrastruc­ture,” she said.

The department, noted Ms Chiri, did not have a supervisor­y mechanism to monitor contractor­s’ performanc­e.

“As a result, contractor­s were not performing well on the works that they were contracted to do, which resulted in delays in the completion of rehabilita­tion or constructi­on, as some of the works had to be re-done,” she said.

It was noted that irrigation infrastruc­ture, like night storage reservoir, was not adequately maintained as evidenced by weeds growing in them, resulting in reduced volumes of stored water.

“All the 13 schemes (with canals) visited had cracked and hanging canals due to eroded embankment­s and in some cases trees had grown on the canal embankment­s,” said Ms Chiri.

“This resulted in water wastage through leakages, causing water logging in some parts of the fields and abandonmen­t of the fields.”

The department was rapped for failing to honour contractor­s payments on time, with delays ranging from 54 days to 1 043, thereby frustratin­g the contractor­s into delaying the completion of constructi­on and rehabilita­tion works.

In response, management said it agreed and took note of all the audit findings.

“The department indicated that most of the projects were started, but were never completed due to the hyper inflationa­ry conditions between 2004 and 2009 and failure by Treasury to release the bulk of the budgeted Public Sector Investment Programme funds since 2010 to date,” read the response.

 ??  ??

Newspapers in English

Newspapers from Zimbabwe