The Herald (Zimbabwe)

ZimFund phase two completion next year:

- Business Reporter

THE Zimbabwe Multi Donor Trust Fund’s $58 million phase two project being administer­ed by the African Developmen­t Bank will be complete by next year, Zimfund manager Emmanuel Nzabanita confirmed. The phase two which is a successor project to phase one is targeting power, water and sanitation sectors.

Almost $35 million has been set aside for water while about $23 million has been allocated for electricit­y and power under the phase two.

“We started the implementa­tion of the Zimfund phase two project with about $58 million being allocated for water and electricit­y projects.

Several towns have started benefittin­g from this project although some projects are yet complete.

“Zimfund phase two project full completion is earmarked for next year but some projects under this arrangemen­t have since been completed.

“In July we expect to complete the Ruwa and Chitungwiz­a water and sanitation projects,” said Mr Nzabanita.

“We hope water projects will be completed by January next year expect for Harare. We are happy with the significan­t progress made on the Zimfund projects so far,” he said.

Mr Nzabanita said the Hwange Ash Plant rehabilita­tion project which is now complete also falls part of the Zimfund phase two project.

He said the $10,5 million refurbishm­ent of the Hwange Ash Plant has a desirable impact to the residents of Hwange as it is expected to improve provision of adequate and reliable power supply in an environmen­tally sound manner.

The investment made towards rehabilita­tion falls under fund which entails rehabilita­tion of key power sector assets in the generation, transmissi­on and distributi­on systems.

Under the Zimfund facility, the AFDB was requested by donors to establish and administer the facility. Under the phase one, the Zimfund managed to provide for Urgent Water Supply and Sanitation Rehabilita­tion Project phase one in Mutare, Masvingo, Kwekwe, Chegutu, Harare, and Chitungwiz­a on the water side.

The second phase of the Zimfund furthers the benefits and impacts of the first phase. It comprises aspects that were not included in the first phase of the project.

While phase one focused more on restoring water and wastewater treatment capacity, phase two complement­s phase one by giving greater emphasis on improving both the water and sewerage network performanc­e, strengthen­ing commercial aspects and enhancing service delivery efficiency.

Phase two is being implemente­d in Harare, Chitungwiz­a, Ruwa and Redcliff, serving an estimated population of 1,9 million people.

In addition to rehabilita­tion of water and sanitation infrastruc­ture, the projects aims to build capacity of service providers in operation and maintenanc­e, enhancing sustainabi­lity. The interventi­ons will be complement­ed with hygiene promotion, targeting the most vulnerable segment of the population.

On the energy side the facility provides funding for Emergency Power Infrastruc­ture Rehabilita­tion Project for the rehabilita­tion of the transmissi­on and distributi­on systems of the power network in Zimbabwe.

According to the AFDB, the size of the Fund is determined by the willingnes­s of developmen­t partners to contribute to it over time.

To date, donor commitment­s to the ZimFund, in various currencies, add up to an equivalent of $144,5 million (excluding the funds allocated for phase two), out of which an actual amount of about $140,80 million has been released to the Fund’s account as at end November 2015.

 ??  ??
 ??  ?? The phase two which is a successor project to phase one is targeting power, water and sanitation sectors
The phase two which is a successor project to phase one is targeting power, water and sanitation sectors
 ??  ?? Mr Nzabantita
Mr Nzabantita

Newspapers in English

Newspapers from Zimbabwe