Zesa raises $116m for Hwange Thermal Power Station

- Felex Share Senior Reporter

ZIMBABWE Power Company (ZPC) has raised $116 million as its equity contributi­on towards the expansion of Hwange Thermal Power Station, paving way for the financial closure of the $1,1 billion project.

The power generating firm has a contractua­l obligation of raising $314 million to cover project developmen­t costs.

The Herald understand­s that the $116 million, enough to kick-start the project, was secured from Standard Bank South Africa ($40 million) and Afreximban­k ($76 million).

The remaining amount would be released as per project requiremen­t.

ZPC’s equity contributi­on was the major condition precedent, which was stalling the financial closure of the project.

Sinohydro, a Chinese firm contracted to carry out the project, told The Herald that China Eximbank — which is expected to release a US$998 million loan for the task — was ready to disburse the funds.

The funding will enable ZPC to add 2x300MW generators, commonly referred to as Hwange 7 and 8, to increase power output from the country’s biggest thermal power plant.

The power station has installed capacity of 920MW.

ZPC acting managing director Engineer Josh Chirukuuts­i said the firm had cleared all outstandin­g issues to pave way for the financial closure.

“ZPC has fulfilled all the conditions precedent for financial closure and we are now expecting the first draw-down for the loan,” he said.

“It is all done and we are only left with processes of disburseme­nt, but by the end of the month we should be able to draw-down from our bank.

“The amount is a lot, but it is going to be released as per project requiremen­t. That is how it is structured.”

Zesa Holdings chief executive Engineer Josh Chifamba said: “Before disburseme­nts are done, there are conditions which should be met. All those conditions precedent have been met.

“What we are now waiting for is disburseme­nt from where we are getting our money, otherwise all the prior outstandin­g issues have been cleared.

“We are waiting for the bureaucrac­y of the banks and from there we will be moving to the groundbrea­king ceremony, which will be done by the highest office in the country.”

ZPC had initially hoped to seal the funding agreement with Sinohydro in 2016, but missed the time line due to unfulfille­d conditions.

The latest developmen­t comes at a time Sinohydro has completed the first unit of the Kariba South power expansion, which is now adding 150 megawatts to the national grid.

The remaining unit, with capacity to churn out another 150MW, is expected to be running by March.

The projects are part of ZANU-PF’s economic recovery programme under the Zim-Asset Infrastruc­ture and Utilities Cluster.

Sinohydro chief representa­tive in Zimbabwe Mr Yifeng Wu said of the Hwange project: “On our part, we are ready and China EximBank is ready and we hope the first disburseme­nt will be happening soon as per projection­s and the project officially commences.

“As the contractor, we are doing preparator­y works, while manufactur­ers in China have already started the manufactur­ing of the main equipment needed for the project. All the agreements and documents are in place.

Parliament has ratified the Hwange project loan and a power purchase agreement between Sinohydro and the Zimbabwe Electricit­y Transmissi­on and Distributi­on Company is in place.”

Zimbabwe Energy Regulatory Authority (ZERA) has approved a tariff of 11c/kWh.

The projects being carried out will see Zesa cutting on power imports, which are costing the power utility.