The Herald (Zimbabwe)

ZPC to start Harare re-powering project

- Golden Sibanda Senior Business Reporter

THE Zimbabwe Power Company (ZPC) will commence re-powering project for Harare Power Station (generator number 2) in the first quarter of this year in a developmen­t that will add 60 megawatts to the national grid and further cut imports.

This comes after the US$533 million Kariba South Power Station extension, which was completed in March last year added 300 megawatts to the national power grid, whittling daily electricit­y imports from an average of 450MW to just 50MW.

Zimbabwe’s peak period demand stands at 1 600MW against internal generation of 1 400 1 500MW, but with the economy currently subdued, Government continues to invest in building capacity as demand will grow when the economy recovers.

Current investment in building internal power generation will stabilise domestic power supply, make Zimbabwe self-sufficient on power, build excess capacity to export and save the country significan­t amounts of much needed foreign currency.

ZPC, the generation unit of State power utility ZESA, is implementi­ng the re-powering project.

ZPC project manager Emmanuel Manyau told a parliament­ary portfolio committee on mines and energy, which toured Harare Power Station yesterday for familiaris­ation, that the project was ready to start after ZPC had secured a $176 million loan.

However, Mr Manyau said out of the US$176 million secured from Afreximban­k, only US$52 million had been earmarked for the Harare Power Station re-powering project while the balance is meant for Hwange Power Station 7 and 8 extension.

Mr Manyau said the project will require US$104 million, but the constructi­on contract with Jaguar Overseas of India, whose officials were in the country recently to discuss implementa­tion following financial close, will cost US$70 million.

It is expected that the re-powering project will take two years to complete, barring unforeseen challenges since the engineerin­g procuremen­t and constructi­on (EPC) contract was already in place after an agreement signed with Jaguar Overseas of India in 2014.

Apart from reducing the country’s need to import power, the Harare Power Station re-powering project will enable the country to reduce internal power deficit, improve efficiency and reliabilit­y.

“Our objective is to revive Harare Power Station number two. Currently, we have Harare Power Station 3, and that is the one that is operationa­l. Harare Power Station number 2 (was) de-commission­ed (in 2014), so that is where our project is focused.

“This project is ready to commence, why do I say

so? licence contract impact agreement The assessment has feasibilit­y with was been Jaguar, signed acquired, study from we with has do EMA we have been ZINWA (and) have an done, environmen­tal a signed for water generation the an supply steam EPC turbines,” The scope Mr of Manyau the re-powering said. project involves replacemen­t of nine chain grate boilers with new technology, which is called circulated fluidised combustion boilers.

The new technology will add two boilers, which will replace the nine boilers.

Each of the boilers will have capacity of 30 megawatts and the new technology comes with advantages of its own, which is the reason the power utility resolved to adopt it.

Mr Manyau said the new technology of the boiler system had higher efficiency, meaning ZPC can use both high and low quality coal at the thermal power station.

The other advantage is flexibilit­y in terms of fuel; these types of boilers are flexible in the type of fuel that they can work with. They can work with high quality and the poorest of quality, which allows us to get fuel from the various local mines.

The system produces low sulphur oxide and nitrogen oxide emissions, which are harmful substances and major issues in terms of environmen­tal concerns or pollution.

Part of the scope of the re-powering project entails refurbishm­ent of turbines and generators, which will not be changed after a life assessment that was done indicated refurbishm­ent could add 15-20 years on the life of the generators and turbines.

“So it was cost effective to keep them, a total of four; two are 10MW and other two 20MW to make a total of 60MW. Our projected start date, we are projected to start within the first quarter of 2019 and we are also projecting to end, all things being equal in the first quarter of 2021,” Mr Manyau told the parliament­arians.

“We anticipate that this project will provide an improvemen­t in generation, which will in turn close the deficit that we have in our supply and demand of power.

“As you know we do have a (power) deficit, so this (re-powering) project for 60MW will significan­tly cover the deficit that we have, especially if you look at the peak time deficit.

“We will be able to have our (power) station running as base load.

“We also anticipate creation of employment and this is obviously during implementa­tion of the project as well as well as after the project has been fully implemente­d and Harare 2 Power Station is now running we will require more people to man it.”

 ?? — Picture by Innocent Makawa ?? Members of the Parliament­ary Portfolio Committee on Energy and Power Developmen­t tour the Harare thermal power station yesterday.
— Picture by Innocent Makawa Members of the Parliament­ary Portfolio Committee on Energy and Power Developmen­t tour the Harare thermal power station yesterday.

Newspapers in English

Newspapers from Zimbabwe