The Herald (Zimbabwe)

US $14m funding for Gwanda solar

- Business Reporter

THE 100 megawatt (MW) Gwanda solar project has received fresh impetus after a local infrastruc­ture fund, African Transmissi­on Corporatio­n ( ATC) Holdings, agreed to extend US$14 million to finance the first 10MW of the project under a phased constructi­on model.

ATC financed the 2,5MW Phase One of the 25MW Centra grid Photo Voltaic project in Nyabira, which entered commercial operations on August 1, 2019 while Phase Two of 22,5MW will commence shortly once funder’s due diligence is completed.

If it materialis­es, the funding provides an avenue and opportunit­y for Gwanda solar, dogged by controvers­y of alleged financial misuse, abuse and implementa­tion delays, to contribute to reducing the country’s crippling power deficit.

The financing from ATC presents alternativ­e source of funding for the Gwanda project, which has been delayed by financial resource constraint­s and also further weighed down by the contractua­l dispute between the parties, which has spilled into the courts.

This was after the Zimbabwe Power Company attempted to cancel the contract last year, citing breach of contract by contractor, Intratrek Zimbabwe with the latter approachin­g the High Court to contest the cancellati­on. This saw Justice Tawanda Chitapi ruling that the contract remained extant, valid and enforceabl­e.

ZPC appealed against Justice Chitapi’s ruling at the Supreme Court, but Intratrek won an order at the High Court for execution pending appeal, which saw the court going the extra mile to prescribe timelines within which the parties should meet and map a way forward.

The Gwanda project developers, Intratrek Zimbabwe, said in a letter to project owners, Zimbabwe Power Company (ZPC), that progress on the Centragrid project attested to ATC’s capability to also progress Gwanda, which will be developed in phases.

“Further, the 10MW, upon commission­ing, would act as successful precedent upon which financing for the balance of 90MW would be mobilised,” Intratrek said

While Intratrek had hoped to secure funding for the Gwanda project, which was awarded at an EPC contract of US$172 million, before the contractor revised it down to US$139 million, the strategy fell apart because Sinosure, which guarantees Chinese public loans, cited arrears on earlier State guaranteed loans to Zimbabwe.

Intratrek also claims alternativ­e funding proposals that included using Afreximban­k and local pension funds, led by CBZ Bank, also received little favour and support from owners of the project, ZPC.

The fund raising has also lately been made more difficult due to perception­s of risk associated with monetary changes that saw Zimbabwe ditch the US dollar for its local currency, which has faced volatility due to exchange rate dynamics and inflation.

“In order to adequately present this financing proposal to ZPC, Intratrek has invested in a review of the project, which culminated in authorship of strategic review document by our consultant­s on what needs to be done to implement the project.

“A reading of this comprehens­ive report dovetails into a coherent strategy which, if embraced, will allow for the commenceme­nt of constructi­on before the end of 2019 and have operating 10MW PV plant by the end of the second quarter of 2020.”

This comes amid indication­s that 90 percent of pre-commenceme­nt works for the Gwanda solar plant have since been completed and these include ground clearing, fencing, signage, geotech and topographi­cal surveys, feasibilit­y studies, roads, temporary offices and ablution facilities.

“The extent of capital outlay invested in the pre-commenceme­nt works makes the project a good candidate to proceed with commenceme­nt, especially in light of available offer on funding the first 10MW,” Intratek said.

ATC has proposed that Intratrek Zimbabwe must agree with the amendments to the engineerin­g, procuremen­t and constructi­on contract with ZPC, finalise all licences and permits, contracts, power purchase agreements and leases by end of this month.

It has also recommende­d that all documentat­ion be submitted to the ATC board by mid next month and that all conditions precedent be fully met by end of December 2019.

ATC indicated that if all is in place, the first draw down could be ready by beginning of February next year.

“This is a very tight timeframe, which leaves little room for errors. There is a need for a co-ordinated front between Intratrek and ZPC to accelerate the project, especially with regards to the applicatio­n to ZERA and negotiatio­ns of the power purchase agreement with ZETDC.

“Recent experience on the Hwange expansion, Mutare peaking project and Gairezi hydro-electric projects, among others, has demonstrat­ed that agreements can drag on without resolution.

“It is important that the implementa­tion agreement should be presented as early as possible to the Ministry of Finance and Economic Developmen­t to get their buy in ahead of time in order to avoid protracted negotiatio­ns and possible delays,” ATC said.

Intratrek executive chairman Wilson Manase, confirmed the developmen­t and said after granting of the High Court order for execution pending appeal, all his company was awaiting are outstandin­g necessary approvals from ZPC.

“All things being equal, we expect to commission Phase 1 by the second quarter of 2020,” he said.

Intratrek technical partner, CHiNT Electric, Vice President Lin Bosheng, said regardless of the funding challenges and hurdles “we have faced, which are mainly associated with sovereign risk and the illegal sanctions imposed on Zimbabwe, we remain committed to implementi­ng the 100MW project and many more in the shortest possible time.”

However, the Gwanda project faces fresh hurdles in the form of ZPC’s indifferen­ce, after the State power utility registered reservatio­ns about progressin­g the project using the proposed funding from ATC, saying the issue of the Gwanda contract was a contested one, as there was a legal case before the courts.

“Please note that the implementa­tion of Gwanda 100MW solar (power) project is in dispute with the case pending before the Supreme Court of Zimbabwe.

“The basis of this dispute emanates from the validity of the EPC contract executed between ZPC and Intratrek. We currently await determinat­ion of the matter by the Supreme Court, as the validity of the contract goes to the root of the project,” ZPC said.

ZPC said they would not consider any variations to the contract — to accommodat­e the ATC funding proposal — to the implementa­tion of the project and that it would be considered as agreed in the initial EPC contact until a determinat­ion on its appeal is reached by the Supreme Court.

 ??  ?? Finance and Economic Developmen­t Minister Mthuli Ncube says budget bids submitted by line ministries indicate resources requiremen­ts of $112 billion, which far exceed the total resource envelope for 2020 Budget which is at $28 billion. Minister Ncube, however, said the ceiling is being revised upwards from $28 billion by a factor of above 30 percent
Finance and Economic Developmen­t Minister Mthuli Ncube says budget bids submitted by line ministries indicate resources requiremen­ts of $112 billion, which far exceed the total resource envelope for 2020 Budget which is at $28 billion. Minister Ncube, however, said the ceiling is being revised upwards from $28 billion by a factor of above 30 percent

Newspapers in English

Newspapers from Zimbabwe