The Herald (Zimbabwe)

Covid-19 delays Batoka power project

- Harare, Zimbabwe, Wednesday 14 April 2021

DEVELOPERS of a US$4 billion hydropower plant on the Zambia- Zimbabwe border have delayed the project until next year because of coronaviru­s.

Pre-constructi­on work on the Batoka Gorge project has been suspended for several months because of the virus and funding is still being secured, Zambezi River Authority spokesman Fitzgerald Muchindu said.

Work on the 2 400-megawatt facility had been scheduled to start in 2020.

“The authority and the developer are doing everything possible to expedite the outstandin­g pre- constructi­on activities with a view to commence constructi­on works at the earliest possible time,” Mr Muchindu said.

“Constructi­on activities are currently projected to commence towards the end of 2022.”

Zimbabwe and Zambia in 2019 chose General Electric and Power Corporatio­n of China to build the plant on the Zambezi River.

The Zambezi River Authority, jointly owned by the government­s of Zambia and Zimbabwe, picked GE and Power Corporatio­n out of a short-list that also included Salini Impregilo, the Italian firm that built the Tugwi-Mukosi Dam.

Other bidders were a joint venture comprising Three Gorges Corporatio­n, China Internatio­nal and Water Electric Corporatio­n, while the other bidder was the China Gezhouba Group.

The Batoka project was first planned for in 1992, but was delayed by an impasse over colonial era debts and community resistance.

The Batoka power plant is expected to take six years to complete but electricit­y generation should start in the third year.

The project will comprise a 175m-high dam wall, two 1,200 MW power plants on either side of the river, a substation, transmissi­on, as well as a new settlement and road infrastruc­ture.

The height of the dam wall was reduced as a response to concerns by tour operators in Victoria Falls that water back-flow would hurt their operations.

Both southern African nations struggle with electricit­y shortages because of poorly maintained equipment and droughts that curb output at existing hydro-power facilities on the river.

In February, the two nations delayed planned upgrades to Kariba Dam, their main source of electricit­y.

Power generation from Kariba collapsed in 2019 after the worst drought in 40 years slashed output, raising some concern over the future viability of hydro given climate change.

Zimbabwe is also developing two coalfired generation units at Hwange to add 600MW to the national grid by 2022.

That project too, has been slowed down by Covid-19 and payment delays to the contractor, Sino Hydro.

“At the end of the (2020 fourth) quarter, constructi­on of the Hwange 7 and 8 expansion project was at 58,29 percent against a target of 78,5percent, yielding an unfavourab­le variance of 17,51percent. This was mainly attributed to the Covid-19 pandemic and the outstandin­g IPC (Interim Payment Certificat­e) payments on the 85percent by China Exim Bank,” the Zimbabwe Power Company says in its latest project update. - Bloomberg.

 ?? FISH4 ?? Lands, Agricultur­e, Fisheries, Water and Rural Resettleme­nt Deputy Minister Douglas Karoro (right), chats with European Union ( EU) Ambassador to Zimbabwe Timo Olkkonen (centre) and UNFAO sub-regional coordinato­r for Southern Africa and country representa­tive Mr Patrice Talla Takoukam (left) during the official launch of Africa, the Caribbean and the Pacific ZimbabweTi­lapia Farming developmen­t inception in Harare yesterday. — Picture: Memory Mangombe
FISH4 Lands, Agricultur­e, Fisheries, Water and Rural Resettleme­nt Deputy Minister Douglas Karoro (right), chats with European Union ( EU) Ambassador to Zimbabwe Timo Olkkonen (centre) and UNFAO sub-regional coordinato­r for Southern Africa and country representa­tive Mr Patrice Talla Takoukam (left) during the official launch of Africa, the Caribbean and the Pacific ZimbabweTi­lapia Farming developmen­t inception in Harare yesterday. — Picture: Memory Mangombe

Newspapers in English

Newspapers from Zimbabwe