New hospital wing opens in May

- WITH ZIMPAPERS KNOWLEDGE CENTRE

The Rhodesia Herald, January 23, 1974

THE new Andrew Fleming Hospital complex is scheduled to open its doors to the first patients at the beginning of May.

And the Ministry of Health says: “We do not expect any serious difficulty in staffing the hospital.”

Phase One of the multi-million dollar complex, the largest single constructi­on job handled by the Rhodesian Government, is nearing completion.

Situated just behind the Central Hospital, one wing of the first phase, which will accommodat­e 130 beds, has already been handed over to the Ministry of Health.

The Ministry will soon start moving in X-ray and other equipment.

The wing contains an accident and emergency unit, two theatres, two X-ray rooms, a resuscitat­ion room and the new four-bed bays, each with its own bathroom and toilet, which are a special feature of the hospital.

Ultra-modern features include an intercom system between patients and nurses.

Each bed will be electrical­ly connected to a central control panel so that nurses can speak to patients without having to walk the length of a hospital block unnecessar­ily.

The remaining section of the Phase One block, which is nearly ready for handing over to the Health Ministry, will accommodat­e an initial 210 beds, according to the controllin­g architect of the complex, Mr Tom Chaman.

A spokesman for the Ministry said the completed wing of the Phase One block would be staffed by more than 200 people.

They include a matron, seven senior sisters, 36 sisters, 64 student nurses, 35 ward attendants, as well as radiograph­ers and physiother­apists.

Work is already well under way on Phase Two which will be the service centre of the hospital, taking in the kitchen, pharmacy, stores, nine theatres, the central sterile supply department, and the main X-ray rooms.

Mr Chaman said constructi­on work was currently on schedule and no delays were anticipate­d. Phase Two will be completed by August next year.

Early in 1975 work will begin on Phase Three, which comprises teaching wards, laboratori­es and libraries.

The entire project, which will cost more than $25 million and will include road works and parking lots, is scheduled for completion in 1981.

The project manager, Mr Frank Holmes, said yesterday overall costs would be slightly up on the initial assessment.

“This is allowing for normal inflationa­ry trends although the increase has been kept to a minimum.”

Mr Holmes said there had been no major snags so far. “We’ve run into plenty of small problems but we’ve managed to solve the lot and basically constructi­on work Is on schedule.”

It was likely that the entire Phase One block, with a total of more than 300 beds, would be operating fully early next year.

LESSONS FOR TODAY

The Parirenyat­wa Group of Hospitals is this year celebratin­g its Golden Jubilee.

◆ Known previously as Andrew Fleming Hospital that catered for the white community, it was renamed Parirenyat­wa Group of Hospitals soon after independen­ce in 1980, and caters for all racial groups in the country. ◆ Apart from the general medical care and surgical sections, the hospital also has a maternity section — Mbuya Nehanda; and, an eye treatment section — Sekuru Kaguvi; and, an annex for psychiatri­c care patients. It is also the country’s biggest referral centres. ◆ The hospital now has 5 000 beds

and 12 theatres and treats hundreds of outpatient­s on a daily basis.

◆ The Second Republic has stressed its commitment towards improving the country’s healthcare delivery system through the constructi­on of clinics; rehabilita­tion/refurbishm­ent of existing facilities; the acquisitio­n of specialise­d medical equipment like ambulances and the magnetic resonance imaging equipment recently, installed at Mpilo Central Hospital in Bulawayo.

For historical informatio­n contact: Zimpapers Knowledge Centre at Herald House on: +263 8677 004323; +263 0242 795771 E-mail: knowledgec­entre@zimpapers.co.zw

Newspapers in English

Newspapers from Zimbabwe