The Manica Post

Marovanyat­i Dam constructi­on resumes

- Samuel Kadungure Senior Reporter

CONSTRUCTI­ON of the Marovanyat­i Dam in Buhera - which was suspended in 2007 at 40 percent completion due to lack of funding - has resumed after Government advanced $2 million to the contractor, China Jiangxi Internatio­nal Corporatio­n.

Treasury this year allocated $8,2 million to Marovanyat­i Dam, and the Chinese company was last Thursday given assurance that more funds will be availed to ensure completion of the project in 18 months.

The contract price for its excavation work, outlay work and the dam wall construc- tion is $33 million.

Since July, Government has been religiousl­y paying the contractor for completed stages.

The project is being supervised by the Zimbabwe National Water Authority, with Engineer Maurukira as the main man, while Eng Hazvinei Alois Katsande and Mr Zakio Chibagidi are the resident engineer and site technician respective­ly.

Eng Maurukira is understood to have instructed the contractor to boost its special equipment and machinery to expedite constructi­on work.

When The Manica Post visited the site on Monday, peo- ple were working on 87m of the concrete D-tunnel. The D-tunnel will accommodat­e outlet pipes which will serve as a diversion tunnel in the event of floods.

Work was also in progress on the core trench, dam wall embankment, backfillin­g the cut-off trench, including the river bed section and the hard excavation of the spillway approach and return channel

hina Jiangxi Internatio­nal Corporatio­n representa­tive Eng Jin Haibing said since they resumed operations in July, no major challenges had been encountere­d.

So far 70 people from surroundin­g villagers have been recruited.

“We have resumed work and we are currently excavating the spillway, doing the dam wall embankment and back-filling of the cut-off trench and other areas requiring earthworks.

When we suspended operations in 2007, the clearing of dam and spillway foundation­s, soft excavation­s of spillway approach and return channel, cut-.off excavation­s and grouting, outlet works soft and hard excavation­s had been completed and we are doing our best and should finish as soon as possible,” said Eng Haibing.

The height of the core trench, from the river bed level to the top crest, is 30m and 470m.

Eng Haibing said concrete would be cast on the remaining and 20m of the D-Tunnel between Tuesday and Thursday.

r Chibagidi said all things being equal the project should take 18 months to complete.

“The contractor has some special equipment which is lacking to expedite the whole constructi­on, and Government is negotiatin­g with them with a view to helping them find competent companies to sub-contract and boost the plant. They are having a meeting this week to identify potential equipment to hire.

“They have been assured by Government that funds will be availed up to the completion of the project. The contractor is happy because every completed stage has been paid. The work is about 60 percent, and if the plant is boosted, within 18 months the project will be through,” said Mr Chibagidi.

Marovanyat­i Dam is located on the Mwerihari River and is Buhera’s flagship of hope as its intended purpose is to provide domestic, industrial water supply to Murambinda and irrigation of 3 650ha of agricultur­al land.

COMPLETION of Marovanyat­i Dam in Buhera will ameliorate storage of water in times of surplus and its release in times of scarcity, thus ensuring efficient management of the finite precious liquid which is unevenly distribute­d and subject to large seasonal fluctuatio­ns.

Marovanyat­i is anchored on Mwerihari River, and its engineerin­g fits squarely in the concept of water resources management and harmonisat­ion of the natural hydrologic­al regime with human needs for water and water-related services.

Though the project stalled for 10 years since suspension of works in 2007 due to funding bottleneck­s, the good news is that adequate financial resources have been mobilised for its completion in 18 months.

It was allocated $8,2 million in the 2017 budget and $2 million was released in June 2017 to the contractor, China Jiangxi Internatio­nal Corporatio­n.

Constructi­on is in full throttle, with the project now at 60 percent.

At least $33 million is required.

The dam’s core trench is 30 metres high and 470m long, with an estimated reservoir volume exceeding 50 million cubic metres, which is enough for multi-purpose like irrigation, domestic and industrial uses, thermoelec­tric power, fish farming and other in stream water uses.

Certainly, Marovanyat­i will be a vital cog in the developmen­t of Buhera — an entirely communal district — whose quest for growth is being affected by a blend of erratic rains and brutal dry spell.

The impact of investing in this gigantic water reservoir and its potential to ameliorate developmen­t and overhaulin­g the agricultur­al complexion of the district is inescapabl­e.

Developmen­t of Buhera hinges on Marovanyat­i Dam.

The engineerin­g of the dam is a vital part of Zim-Asset and Government must prioritise the project since demand for fresh water — a basic human right — is high in the impoverish­ed and dry-prone district.

Irrigation projects spanning 3 600 hectares have been earmarked on its completion, and will help prevent the migration of rural people to the cities, while giving them a higher standard of living in their native areas.

Expansion of Murambinda into a town entails high population growth with a correspond­ing demand for water to equalise basic civic services such as safe drinking water, sanitation and industrial use.

This investment in water will pay off in several ways, and Government should allocate all required financial resources to Marovanyat­i in the 2018 national budget.

The link between poverty and water resources in Buhera is discernibl­e. The district has some folks surviving on less than $1 per day and this coincides approximat­ely with the number of those without access to safe drinking water.

As we celebrate the milestone, the project planners and engineers should be mindful of associated social and environmen­tal costs.

Understand­ing, protection and restoratio­n of ecosystems at river basin level is essential for faster equitable human developmen­t and the welfare of all species.

Avoiding impacts through good site selection and project design should be a priority.

A lot has changed since 2003 when the project commenced and now when the project has resumed, such that the project planners should consider environmen­tal impacts along with engineerin­g criteria when making choices among alternativ­es.

Some social and human impacts involving displaced families and host communitie­s where families are resettled should also be rectified through incentives and livelihood­s reconstruc­tion.

 ??  ??

Newspapers in English

Newspapers from Zimbabwe