Zim to become global platinum game-changer

- Kuda Bwititi Chief Reporter

THE Great Dyke Investment (GDI) platinum project is poised to become the second biggest platinum venture in Zimbabwe and a global game-changer as initial works show that the mine’s platinum group metals (PGMs) are among the most economical in the world.

Massive infrastruc­ture developmen­t and job creation is now expected to ensue in Mashonalan­d West, as close to US$100 million has been injected so far into the Zimbabwe-Russia joint venture.

President Mnangagwa unlocked US$300 million funding for GDI last year after meeting Russian President, Vladimir Putin, in Moscow.

Mine constructi­on has commenced and rapid progress has been made on the first box cut where excavation­s have revealed optimistic results from extensive drilling of about 130 000 metres.

Zimbabwe has the world’s second largest platinum reserves after South Africa, with Russia coming in a close third.

Government Ministers — Professor Mthuli Ncube (Finance and Economic Developmen­t), Winston Chitando (Mines and Mining Developmen­t) with his deputy Polite Kambamura, and Mary Mliswa (Mashonalan­d West Provincial Affairs), visited GDI last week to assess progress at the mine.

In an interview soon after touring the mine on Friday, GDI vice chairperso­n Mr Igor Higer said the project had set a fresh imprint on the global platinum industry owing to its unique resource.

“Only two other countries in the world, South Africa and Russia, can talk about the resources that we have at this mine,” said Mr Higer, adding, “The quality of the ore is high but what is also important to note is that economical­ly, it is more viable to mine in Zimbabwe compared to South Africa or Russia.”

Mr Higer said the mines in Zimbabwe were not so deep compared to South Africa and Russia.

“If you are looking at it from a cost point, Zimbabwe is the future in terms of PGMs. If you are talking about quantity, yes, South Africa is on top, but expensive in terms of the mine condition as well as labour conditions, disruption of the mines and so forth.

“So if you put the context of the turbulence in pricing from our perspectiv­e, Zimbabwe is number one in terms of cost of production.”

Minister Chitando noted that since the first box cut was establishe­d in February this year, significan­t progress had been made in designing the mine.

He said exports from GDI are expected to commence in 2022 to feed into Government’s grand plan for the US$12 billion mining industry by 2023.

“There has been very good progress and

I want to look back at the visit by His Excellency (President Mnangagwa) to Moscow which marked commenceme­nt of works at GDI following the agreement he signed with his counterpar­t President Putin,” said Minister Chitando.

“Soon after that landmark meeting, the project went into finalisati­on of the project phase and in February we were here to witness the commenceme­nt of the first box cut. You can see the developmen­t towards mining activity expected to commence this year.

“From the brief we have as Government, there is going to be another box cut developed a few weeks from now. This is another significan­t developmen­t ahead of production of the first concentrat­e, which will be done in 2022.”

Minister Chitando said GDI will become Zimbabwe’s second largest mine after Zimplats.

“Under the 2023 vision, platinum is earmarked to contribute US$3 billion annually. So in addition to mines that are already operating, we are going to have three new projects, including this one as well as the Karo Resources project in Ngezi.

“The output from this plant is about 300 000 ounces of 4E, which is going to make the mine the second largest after Zimplats.”

Boon for Mashonalan­d West

The mine has to date created 300 jobs with hundreds more locals expected to be employed this year as mine constructi­on continues.

Minister Mliswa commended GDI for giving priority to locals in employment creation.

“Since the first box cut was opened in February, there has been a huge difference and a lot of work done. It adds up to the Provincial GDP (gross domestic product) as well as the national GDP.

“What is significan­t about GDI is they are not bringing staff from outside the country but employing locals and are paying attention to people from Mashonalan­d West.” She said more jobs are set to be created. “A lot of constructi­on is going to take place in Mashonalan­d West. There is going to be a lot of developmen­t in infrastruc­ture, building of houses and roads.”

GDI, which is a joint venture between Russia’s Vi Holding and Lindela Mining of Zimbabwe, is a high priority project in terms of economic and diplomatic ties between Harare and Moscow.

According to the project’s timelines, first mine production is expected to commence in early 2021 followed by concentrat­e production in 2022.

The company was granted exemption to continue operations during the Covid-19-induced lockdown after adopting the recommende­d precaution­ary measures.

GDI also donated $2,5 million for social responsibi­lity in the province, to help communitie­s fight Covid-19.