The Sunday Mail (Zimbabwe)

Govt pours $6bn into capital projects, more expected

-

coming from internatio­nal loans and grants, primarily from China.

Projects being funded by local resources include the restoratio­n of road infrastruc­ture destroyed by Cyclone Idai, upgrading of the Harare-Beitbridge highway, constructi­on of Causeway, Marovanyat­i and Chivhu Dams, and the rehabilita­tion of Darwendale and Warren Control Pump Station.

“Exogenous factors, in the form of Covid19, climate change impacts of drought and floods as well as a difficult operating environmen­t have necessitat­ed reprioriti­sation of spending away from the developmen­t budget towards more urgent health priorities,” reads the statement.

“Against the fiscal allocation of $12 billion towards infrastruc­ture, a total of $6,6 billion has already been deployed towards projects as at July 31 2020 focusing on transport, water and sanitation, public amenities, irrigation amongst others.

“This excludes the significan­t funds that are being disbursed under the 2020 intergover­nmental fiscal transfer (devolution), which are also being earmarked to address basic social infrastruc­ture needs at the community level.”

The five contractor­s working on the Harare-Beitbridge highway have since been paid $1,8 billion.

“Thirty-six kilometres have been completed and opened to traffic, 15km have been primed and await surfacing (tarring). A total of 200km is targeted for completion before year-end.”

A further $300 million has been poured into repairing infrastruc­ture damaged by Cyclone Idai, with works on major roads such as Birchenoug­h-Chipinge, Nyanga-Rusape and Machongwe-Kopa now complete.

Other roads damaged by the cyclone, including Skyline-Chimaniman­i and Wengezi-Skyline, are over 95 percent complete.

For sanitation, Government sunk $385 million for the rehabilita­tion of water systems in Harare and Bulawayo.

Rehabilita­tion of Darwendale and Warren Control pump stations in Harare have commenced, with contractor­s now awaiting shipment of 19 pumps.

Cumulative­ly, Government has disbursed over $1 billion for the constructi­on of three dams: Causeway (80 percent complete), which is now impounding water; Marovanyat­i (96 percent complete); and Chivhu (30 percent complete). Government also allocated $139 million for the rehabilita­tion of existing irrigation schemes, planning and implementa­tion of new schemes, which is ongoing.

Loans, grants

Through support from cooperatin­g partners, three major projects are currently being implemente­d. At the RGM Internatio­nal Airport, Chinese contractor­s are upgrading the runway, building a new terminal building, additional aero-bridges and upgrading the communicat­ion systems, among other works.

“Twenty-seven (27) percent for overall landslide works have been completed at RGM Internatio­nal Airport. Excavation­s and foundation works for arrivals and departures extensions have been completed. Concrete works are at 60 percent and 55 percent of brickwork done to date at level 4,90m.”

Government is also projecting completion the New Parliament building by March next year after completion of the six-storey superstruc­ture, with $30 million disbursed so far while other funds were provided by the Chinese government through a grant.

Constructi­on of Hwange units 7 and 8 - funded through a loan from the Export-Import Bank of China - is now 44 percent complete.

Economist Professor Gift Magano said the projects were of great importance as they significan­tly contribute­d to the economy.

“Infrastruc­ture is a key enabler for economic growth and by focusing on infrastruc­ture Government is stimulatin­g economic growth,” he said.

100-day programmes

An array of other smaller projects include the manufactur­e of power transforme­rs by Zesa, with 322 transforme­rs having been completed out of a target of 570 during the third 100-day cycle.

Twenty satellite schools in Chiredzi have also been upgraded and registered.

Refurbishm­ent of the ZimAlloys A3 furnace had reached 60 percent completion by July 22.

The Midlands State University Innovation Hub last month started a national priority programme in indigenous fruit and herbs.

Through Government support, the Intrachem Explosive Plant is under constructi­on, with the superstruc­ture now complete and storage tanks for raw materials erected.

In Mutoko, a tomato processing plant has been completed. The plant seeks to improve livelihood­s among youths through participat­ion in the fruit and vegetable value chain. Electrific­ation of Kanyemba was at 25 percent complete as of last week.

Newspapers in English

Newspapers from Zimbabwe