The Zimbabwe Independent

Chinese companies ditch Zim projects

- Andrew Kunambura/Tinashe Kai riza

MAJOR Chinese insurance firms are refusing to underwrite critical infrastruc­ture projects in Zimbabwe due to government’s failure to pay commitment fees and other related costs, it has emerged.

Official sources say the constructi­on of the US$680 million Kunzvi Dam, for which the tender was awarded to Chinese state enterprise Sinohydro, has stalled after government dithered on paying the required US$10 million commitment fee, prompting one of China’s top insurance firms Sinosure — which has to date funded projects worth billions of dollars in Zimbabwe — to ditch the venture.

The constructi­on of Kunzvi Dam, a highly profitable undertakin­g on completion, has remained in the pipeline since it was mulled in the 1950s when Zimbabwe was then called Southern Rhodesia and was part of a federation with Malawi and Zambia.

The dam has long been billed as the panacea to Harare’s perennial water woes and could spur a massive agricultur­al boom as the site is located in one of the country’s most fertile districts, Goromonzi.

Currently, Harare relies on the heavily polluted and silted Lake Manyame, whose water costs about US$40 million annually to clean.

Although Treasury allocated ZW$258 million (US$3 million) towards the project, sources said it is yet to get the necessary fiscal vote.

Government sources told the Zimbabwe Independen­t this week that as at present, the process of tying the loose ends of the tender has been put on hold because of the Chinese frustratio­n at the lack of commitment by President Emmerson Mnangagwa’s administra­tion.

“There has really been no progress on the project mainly because of government’s lack of commitment. What happens with projects of that nature is that they are underwritt­en by Chinese insurance companies and as of now, we have not paid the required commitment fee amounting to US$10 million and this has greatly

frustrated the Chinese,” an official involved in the processes said.

“So, as we speak, Sinosure is holding on to its money, while Sinohydro is willing to resume work,” the official added.

Another government source said: “In the case of Kunzvi Dam, the tender was awarded to Sinohydro but work has not started because government has not yet paid the initial commitment fees and has failed to honour insurance premiums for previous project.”

Among a myriad of factors stalling some of the projects, the sources added, financiers in China were delaying to release funding because of government’s failure to service its ballooning debt with Sinosure, among other creditors.

“What I understand is that government owes a substantia­l debt to Sinosure which Zimbabwe has not been servicing. This has resulted in the delayed disburseme­nts of funds earmarked for a number of projects,” a Chinese diplomat accredited to Harare said, emphasisin­g that progress had also been slowed by challenges arising from the Covid-19 pandemic.

Chinese deputy ambassador to Zimbabwe Zhao Baogang, however, said he was not in a position to comment on the matter when he was asked about the matter.

“I do not have informatio­n about that. I am not in a possession to comment,” he said.

Apart from the Kunzvi Dam project, other ongoing projects which are in danger of being derailed include the US$1,1 billion expansion of the Hwange Thermal Power plant and the constructi­on of the 2 400 megawatt, US$5 billion Batoka hydroelect­ric power station, for which a feasibilit­y study is already underway.

Both projects, which are of immense economic benefit to the southern African nation, are being undertaken by

Sinohydro.

The constructi­on of Hwange units 7 and 8 is now 52% complete.

Another affected project is the expansion of the Robert Gabriel Mugabe Internatio­nal Airport by Jiangsu Internatio­nal Group of China at a cost of US$153 million. Last year, the Independen­t exclusivel­y reported that the project was temporaril­y halted after government raided US$10 million held in an escrow account meant to fund the programme.

At the time the funds were raided, discussion­s between government officials, particular­ly from Treasury and China’s embassy officials were held to ensure that Zimbabwe would restore the money to allow work to progress. It is not yet clear whether Treasury complied.

The company also undertook the renovation of the Victoria Falls Internatio­nal Airport at a cost of US$150 million which saw the facility’s carrying capacity being significan­tly increased.

Sinohydro also undertook the US$533 million Kariba South expansion project to increase generation capacity by 300megawat­s.

Government and its related department­s, the sources said, were also struggling to craft viable and bankable project proposals, which could attract Chinese banks and insurance firms to inject capital into local projects.

As the Chinese insurance firms turn their attention away from Zimbabwe as a profitable investment destinatio­n, their interest has shifted to other countries on the continent.

A very senior government source said: “A number of viable projects that Chinese state firms had committed to insure and finance risk being abandoned due to government’s failure to pay a range of costs required before work could start. What is clear is that delays on completion of the projects will arise.”

Minister of State for Presidenti­al Affairs in charge of monitoring and implementa­tion of government projects, Joram Gumbo, declined to comment.

“I cannot comment on those issues. You will have to talk to the Finance ministry which is responsibl­e for allocation of funds. My duty is only to monitor the projects and report to the president,” he said.

Both Finance minister Mthuli Ncube and the ministry’s permanent secretary George Guvamatang­a were not available for comment as they were not answering their mobile phones.

Concerns are growing that Zimbabwe is failing to fully utilise the US$60 billion which Chinese President Xi Jinping pledged to finance infrastruc­ture projects in Africa in the form of assistance, investment and loans under the Belt and Road Initiative (BRI) at the Forum on China-Africa Cooperatio­n (Focac) meeting in Beijing in September last 2018.

 ??  ?? President Emmerson Mnangagwa
President Emmerson Mnangagwa
 ??  ?? Chinese deputy ambassador to Zimbabwe Zhao Baogang
Chinese deputy ambassador to Zimbabwe Zhao Baogang