The Railway Magazine

BACK TO THE START:

-

The front section of tunnel boring machine Dorothy has been dismantled and moved back to the northern end of the Long Itchington Wood Tunnel in Warwickshi­re. Breakthrou­gh at the southern end of the first of the twin bores to be excavated took place in July. The front of the TBM, including its 10-metre diameter cutting head, weighing 160 tonnes, was placed upright onto a self-propelled 48-wheel trailer for its night-time return on September 21 to where its journey began. The TBM’s tail skin was also moved during the same operation. The 2.5-mile trip took three hours. Eight other large pieces had been previously moved by road, while the rest was moved back through the tunnel. Dorothy will be reassemble­d to begin work on the second bore later this year.

 ?? HS2 ??
HS2

Newspapers in English

Newspapers from United Kingdom